National Transport Authority: Financial Statements 2024
The committee examined the NTA’s 2024 accounts, with a clear audit opinion but concern raised about major delays and overruns in the national train control centre project. NTA officials said the project is being split into phases to reduce risk, with estimated completion now around 2028 and total cost likely to rise from €148 million to between €175 million and €205 million. Members also pressed the NTA on high legal costs linked mainly to BusConnects, the expensive Deer Park active travel scheme, and the governance of large projects such as DART+ and next generation ticketing. The NTA said public transport and active travel use continued to grow strongly in 2024 and that funding supported higher patronage, new services and infrastructure.
This morning we will engage with the National Transport Authority to examine its financial statements of 2024. On behalf of the committee, I welcome our witnesses: Ms Anne Shaw, chief executive officer; Mr. Hugh Creegan, deputy chief executive; Mr. Philip L'Estrange, director of finance and corporate services; and Mr. Jeremy Ryan, director of public transport services at the NTA. We are also joined by the following who are attending in a representative capacity from the Department of Transport: Mr. Andrew Ebrill, principal officer, and Ms Akriti Brady, principal officer. We are also joined by officials from the Office of the Comptroller and Auditor General, including the Comptroller and Auditor General, Mr. Seamus McCarthy, who is a permanent witness to the committee, and Ms Georgina O'Mahony, deputy director of audit. They are all very welcome here this morning.
Before we begin, I wish to explain some limitations to parliamentary privilege and the practice of the Houses as regards reference witnesses may make to other persons in their evidence. The evidence of witnesses physically present or who give evidence from within the parliamentary precincts is protected, pursuant to both the Constitution and statute, by absolute privilege. This means that they have an absolute defence against any defamation action for anything they say at the meeting. However, they are expected not to abuse this privilege, and it is my duty as Cathaoirleach to ensure this privilege is not abused. Therefore, if their statements are potentially defamatory in relation to an identifiable person or entity, witnesses will be directed to discontinue their remarks. It is imperative that they comply with any such direction.
Witnesses are also reminded of the long-standing parliamentary practice that they should not criticise or make charges against any person or entity by name or in such a way as to make him, her or it identifiable, or otherwise engage in speech that might be regarded as damaging to the good name of the person or entity.
I call the Comptroller and Auditor General, Mr. Seamus McCarthy, to make his opening statement.
Comment on this
The National Transport Authority undertakes a wide range of statutory responsibilities relating to strategic public transport planning, development, regulation and funding. This includes responsibility for ensuring the achievement of a substantial reduction in the level of greenhouse gas emissions from the transport sector.
The authority's income in 2024 amounted to just under €2.3 billion, up from €2 billion in 2023. Most of its income comes from Exchequer grant funding, almost all of which is paid from Vote 31 - Transport. In 2024, this amounted to €1.775 billion.
In addition to covering the authority's running costs, this included grant funding earmarked for a recurrent support of public transport operators and investment in transport infrastructure. The authority receives public transport fare revenue under contract arrangements with the transport operators. In 2024, fare revenue amounted to €501 million, up from €471 million in 2023, mainly reflecting increased public transport passenger volumes.
The authority's expenditure in 2024 amounted to €2.19 billion. Just over half of this, €1.6 billion, was in respect of public service obligations, PSO, payments. These payments are made to the operators of public transport in respect of public transport services that otherwise would not be financially viable. The contracts between the authority and the operators set standards of operational performance and customer service, and control fare setting. The contracts also allow for the authority to impose PSO payment deductions where the operator's performance does not meet contractual standards or to make incentive payments where performance exceeds standards.
The second largest area of spending by the authority is in respect of the provision of capital investment grants to a wide range of bodies. This amounted to just over €882 million in 2024. In addition to the investment funding provided to other bodies, the authority invested €138 million in the purchase of buses that were added to its own bus fleet, which it makes available to public transport operators. The carrying value of the whole bus fleet in the statement of financial position was just under €519 million at the end of 2024.
I certified the financial statements on 13 June 2025 and issued a clear audit opinion. However, I drew attention to the delays and cost overruns on the ongoing national train control centre project. In July 2019, the authority approved an Iarnród Éireann project to develop a new national train control centre to manage and regulate all train movements on the national rail network. The project includes the construction of a new central train control building at Heuston Station, the refurbishment of the existing train control building at Connolly Station, and the development of a new train traffic management system and a related backup facility. While the new building at Heuston Station was completed in 2022, there is significant ongoing delay in the development of the train traffic management system. The original plan was that the new management system and the backup facility would both be commissioned by March 2025. Note 25 to the financial statements discloses that, at the reporting date, the latest estimated date for completion and handover of the system and the backup facility was November 2028. The original budget for the full project was €148 million but the authority estimates the outturn for the project is now expected to be of the order of €189 million. This represents an expected cost overrun of €41 million, or 28%. The chief executive officer will be able to provide the committee with an update on the project progress.
Comment on this
I thank Mr. McCarthy for that. I now invite Ms Anne Shaw to make her opening statement on behalf of the NTA. As set out in the letter of invitation, she has five minutes in which to do so.
Comment on this
I thank the committee members for the invitation to appear before the committee today. I understand the committee wishes to discuss the transport financial statements for 2024. As has been already mentioned, I am joined by colleagues from the National Transport Authority to help with any of the questions that arise from today's session. For brevity, in the opening statement I will only cover some highlights around the key areas of responsibility of the NTA and that are included in the 2024 annual report and financial statement. These address the policy objectives around the economy, climate action and social well-being.
The National Transport Authority is a statutory non-commercial body which operates under the aegis of the Department of Transport. As has already been explained, the remit of the NTA, under various enabling legislation, relates to a variety of responsibilities, which include the planning, development and funding of sustainable transport modes on a national basis; the regulation of commercial bus services and small public service vehicles; and managing an extensive capital programme, including being the approving body for three megaprojects, namely, MetroLink, BusConnects and DART+.
The work of the NTA is guided by a national mobility policy to meet the Department of Transport's ambition for 50% of all journeys to be made by walking, cycling and public transport by 2030, the aim being to ensure the provision of a transport system which benefits people by facilitating and enabling social, cultural and economic development as well as responding to the challenge of meeting carbon neutrality by 2050.
The need for the investment that is being made in transport can be highlighted in two sources of research by the Department of Transport on the impact of congestion on the economic performance within the State, first concentrating on the greater Dublin area, GDA, and then on regional cities. The research identified that, within the GDA, the cost of congestion to society will rise to €1.5 billion by 2040 and €2 billion nationally without intervention and that it will have many other associated social, health and well-being impacts as well. To minimise the cost of congestion, accommodate the growing population and meet climate policy obligations, continuous improvements are needed in sustainable transport in each city, as well as the Connecting Ireland programme covering the non-urban areas. This brings sharply into focus the work of the NTA and its delivery in 2024 towards achieving these targets.
In carrying out its responsibilities during 2024, the NTA engaged with a number of local authorities nationally on the preparation and development of local area plans for key towns and settlements to assist in the prioritisation of transport investment in local areas to support a growing population, tackle rising congestion and address those negative impacts on the economy and the environment. During 2024, ten local transport plans were drafted and consulted on and have helped inform the direction of travel for investment in sustainable transport modes, working closely with those local authorities and communities. The financial statements set out the areas of delivery and investment during 2024. They also set out key successes as well as progressing future programmes through their statutory processes for future delivery working towards the targets mentioned previously.
Some of the outcomes of the work undertaken are captured in the annual surveys conducted during November in Dublin, Cork, Waterford, Galway and Limerick, which show that sustainable travel is on the rise. Within the Dublin region, the annual Dublin canal cordon count identified that 74.1% of inbound trips were made by sustainable transport modes, the highest percentage level since this survey commenced in 1980. In Galway, 43% of journeys across the city cordon were made by bus, rail, walking and cycling, representing an increase of 25% on 2023 figures for bus usage and an increase of 6% on rail journeys. In Cork, while bus and rail movements showed year-on-year increases, overall movement across the cordon by sustainable modes was 23% compared with 75% of car use. Separately, Waterford recorded a 38% increase in bus passengers across the city centre cordon compared with 2023, with inbound trips by sustainable modes across the city cordon totalling 16%. In Limerick, positive increases, albeit small, in each of the sustainable modes were recorded when compared with 2023, with a total of 27% of people travelling inbound towards the city using sustainable modes of travel. These highlight the outcomes moving in the right direction but there is obviously more work to do in all places to meet the relevant targets.
Public transport use continues to grow at exceptional levels. Overall, passenger numbers on contracted bus and rail services in 2024 were 32 million, higher compared with 2023 and an increase of 10.6%. Passenger numbers increased on all service types during 2024, from rural transport to the urban rail services, with the largest increases evident across the network in Dublin. Unlike many other international jurisdictions, overall public transport passenger numbers in Ireland now significantly exceed the 2019 pre-pandemic levels, with 344 million passengers carried on State-provided services in 2024 compared with 295 million in 2019. The increase has been supported by a number of capital projects which have increased capacity for services and provided improved customer experience to facilitate behavioural change as greater choice is provided. The 2024 budget provided an increase in capital expenditure from just over €892 million in the previous year to just under €993 million. Examples within the rail programme include the first of new carriages for the DART fleet being delivered in November 2024 for testing and commissioning; completion of the Limerick Colbert Station transport interchange; improvements on the Cork to Dublin line with the opening of stations enhancing passenger services on the Portlaoise to Heuston commuter route; and the implementation of enhanced timetables for Cork commuter rail services.
On the bus network, a number of new services have been launched as part of BusConnects in Dublin in addition to 45 new or enhanced bus routes introduced as part of the Connecting Ireland programme, including new services on Saturdays and Sundays. This is complemented by provision of new bus shelters, stops and passenger information as well enhancements to bus depots including electrification with the first double deck electric buses operating in Limerick.
The 2024 funding covered over 1,000 active travel projects providing new and improved walking and cycling infrastructure across the country. These projects contribute to reaching the Government’s target of delivering 1,000 km of new and improved walking and cycling infrastructure across the country by the end of 2025, with 938 km achieved by the end of 2024. This is leading to an increase in active travel trips and improving road safety for more vulnerable road users, including outside many schools.
Some €701.1 million of Exchequer funding was provided for public service obligation across rail, bus and tram services. This has generated an additional income of €510.721 million from fares and other revenue sources such as advertising. This funding has enabled increases in service provision and supported the driving up of patronage across all modes.
Operational costs have risen from €982 million to just over €1 billion. This increase is attributable to inflationary pressures on fuel and labour plus the growth in service provision, as well as the decision to maintain low fares in support of the cost of living and other concessionary fare commitments implemented throughout 2024. These factors should be considered when evaluating the overall financial outcome.
In summary, the funding provided and managed by the NTA has facilitated the target to increase more journeys through public transport and active travel and has prepared the way for future years’ investments, which have started to come to fruition during 2025 to meet the various national obligations around the economy, climate and social well-being.
Comment on this
I thank Ms Shaw. We will suspend our meeting at about 12.30 p.m. for a short break and resume shortly afterwards. I will open the floor to members now. The lead speaker today is Deputy Kenny who has 15 minutes. All other speakers thereafter have ten minutes. That will allow members back in for a second round.
Comment on this
I thank the Chair. I welcome the witnesses. I congratulate Ms Shaw on her appointment last year.
I will focus first on the national train control centre on page 124 of the annual accounts. The national train control centre building at Heuston Station was completed in 2022. How much did that building cost?
Comment on this
I will ask Mr. Creegan to respond to these questions. He has the detail on that particular project.
Comment on this
Actually, I do not have the building number straight away but I can come back to the Deputy later in the meeting. From memory, it was around €40 million but if the Deputy lets me check it out, I will come back to him.
Comment on this
Do the witnesses not know how much it cost to build the building in Heuston?
Comment on this
We do but it is part of the overall project. I do not have the actual -----
Comment on this
The overall project budget was €148 million.
Comment on this
Therefore Mr. Creegan is estimating about €40 million.
Comment on this
Let me check it out and get back to the Deputy in a moment, if that is okay.
Comment on this
That is okay. The original plan was that the development of the train traffic management system in the back of the facility would be commissioned by March 2025. The NTA is now saying there will be a delay of three years and commissioning will be in May 2028. Is Mr. Creegan confident of that?
Comment on this
There is still uncertainty about it. This is a complicated project. I will give a tiny bit of context without eating up time. There will actually be three control centres located in this one building. The train control centre will be there, a Garda regional traffic management centre is there with 100 gardaí operating there and there will be a regional road traffic control centre that Dublin City Council is fitting out this year.
Comment on this
We knew that. That is not new news.
Comment on this
I understand. The software and the transition to the new train control system is taking longer than expected. Both the development and testing of the software is taking longer. It was initially intended that it would be done in one singular implementation and that the whole of the country would move onto the system on one particular day. We have taken the view with Irish Rail to divide it into phases to reduce the level of risk. There is a certain amount of risk inherent in doing it in one phase. Now it is being delivered in a series of eight phases. The first phase target for the software is in April this year but the whole testing of it is going to take months so it will be later this year before that first phase is fully completed. While we have given the date of 2028, we can only firm up that date when we see how the first phase has gone and take the lessons out of it and make sure we apply those to the remaining seven phases.
Comment on this
When will the first phase be done?
Comment on this
The software will be developed by the end of April.
Comment on this
The end of April this year when it will be completely developed but then it has to go through a whole testing phase and approval phase, which will take a number of months. It could be the end of the year -----
Comment on this
When the original plan for the management system was to be commissioned by March 2025, was it not seen coming down the line that this would have to be put into phases?
Comment on this
A national train management system is a very rare thing. It does not happen very often at all around the world, and certainly it is a once in a generation thing here in Ireland. The view was taken at the design stage that we should be able to do it in one single phase but since then we have seen what has gone wrong in other projects in various other places like Crossrail in the UK. A more prudent approach is the one being taken now to divide it in phases. There was a conscious decision at the beginning -----
Comment on this
Does Mr. Creegan believe that prudent approach is the reason for the cost overrun?
Comment on this
It is absolutely a significant part of it, yes.
Comment on this
The NTA estimated that a cost overrun of €41 million or 28%. When did it estimate that?
Comment on this
It was 2024. I should be careful and say what we actually estimated was, because there was a range in cost, a range of likely outturn cost would be between €175 million and €205 million with the middle figure – what we call the P50 – of €189 million, which is the figure the Deputy heard quoted. It is still in that range. Given uncertainties, we do not want to pin a figure down. Hopefully it will be delivered in that range. We are just not sure yet until we see the project develop a bit further.
Comment on this
How much has been spent of that original €148 million project budget?
Comment on this
A total of €150 million has been spent to date with €15 million spent on it during 2025.
Comment on this
Therefore €150 million has been spent, the NTA is hoping we are another three years off and it is estimating a €41 million overspend.
Comment on this
We are estimating the final outturn will fall within the range of €175 million to €205 million. The €14 million is a specific figure within that range.
Comment on this
Therefore Mr. Creegan is estimating it could be €22 million over budget or it could be far more significant -----
Comment on this
Within that range I gave the Deputy there - €175 million to €205 million.
Comment on this
Can Mr. Creegan give a guarantee that it will be in that range?
Comment on this
It is very hard in life to give a guarantee about anything but we are giving that as our best expectation, based on the knowledge we have, as to what the outturn will be.
Comment on this
Mr. Creegan will appreciate the significant issue is that if we come around here again in another two or three years, this project might not be completed because, as he said, he cannot give a guarantee it is going to be completed and the significant issue is we do not know and a guarantee cannot be given on whether the significant overspend will continue rising. What we do not want now is another children’s hospital.
Comment on this
It is not that. This is a project that has not gone as well as we would have liked but the approach being taken now with the more incremental delivery of it is a wiser way of delivering it, a safer way of delivering it and a less risky way of delivering it. While I cannot guarantee an outturn price our expectation is what I have said to the Deputy there and all the signals I am seeing is that while there is lots to be done but we should end up in that range ultimately.
Comment on this
Considering the control system will not be up and running until 2028, what is ongoing in that building in Heuston now?
Comment on this
As I said, there are three control centres in the one building. The Garda Dublin metropolitan region control division occupies part of the building and has 100 gardaí there doing their controls, whatever they do, managing the Dublin metropolitan region. Dublin City Council is fitting out a regional traffic control centre, which will become operational later this year.
Irish Rail has moved certain functions into the building, including things such as overhead line control and some level crossing control. Personnel have also moved. I should have said that the incremental approach means that parts of the system will be moving into the building on an incremental basis from this year on. It is not that we have to wait until 2028 before the thing gets switched on.
Comment on this
Was it envisaged when it was completed in 2022 that parts of the Garda and Dublin City Council were going to occupy the building?
Comment on this
It was a fundamental part of the project that we would co-locate a centre. That was in the project plan from day one.
Comment on this
They will not continue to occupy it, however.
Comment on this
They will continue to occupy it. The intention was to put in these control centres where the personnel are in close proximity to each other. When it comes to emergency and crisis management events, it is easier to manage them if everybody is located in the one place. That was the plan from day one.
Comment on this
They will continue to occupy the building.
Comment on this
I will move to general legal costs for the NTA. The general legal costs for 2023 and 2024 amounted to €5.5 million. Will the witnesses give a short indication of what those legal costs were?
Comment on this
The majority of the general legal costs arose through the management of a number of judicial reviews, particularly in respect of the BusConnects programme. That is what accounts for the majority of those costs.
Comment on this
Does the NTA use the same legal company every time?
Comment on this
We have gone through a procurement process to engage a legal firm to deal with our legal issues. That is the best way to get value for money and to ensure we have the right levels of service.
Comment on this
When was that procurement process?
Comment on this
The company would have been procured approximately four years ago, from memory. There are potentially another four years to run on the contract.
Comment on this
The company was given a contract for eight years.
Comment on this
That was to mirror the size and scale of the transport projects that are being delivered, many of them over a long timescale. It made sense to have the same legal adviser.
Comment on this
Is there no obligation on the NTA to put out a procurement every year?
Comment on this
There are extension periods in most of our contracts. The contract can be extended during the envisaged contract term. Those extensions can be confirmed later on. I will come back to the Deputy on the exact number of years confirmed at the outset of the contract and the number of years that are optional extensions. I will come back on that point.
Comment on this
Does Mr. L'Estrange believe that is providing good value for money?
Comment on this
It was a public procurement at the time. We had a lot of interest in the competition. The incumbent won the contract on the basis of a price-to-quality ratio. The answer to the question is "Yes".
Comment on this
In 2023 and 2024, the expenditure was €5.5 million. How much was paid in general legal costs in 2025?
Comment on this
We are finalising the figures for 2025. Today is only 15 January. We have gone through the accounts. They will be subjected to audit, too. It will be a similar figure because we have continued to deal with a number of judicial reviews on projects, working with our colleagues across the wider transport state. It will be a similar figure, but we cannot confirm that to the Deputy today. We will have to come back to him.
Comment on this
The figure will be in or around €3 million.
Comment on this
It will be broadly similar. I will move to the renovation of the entrance of a south Dublin park at a cost of €750,000. Why did the NTA pay for that?
Comment on this
It was part of an active travel scheme connecting cross-county in Dún Laoghaire-Rathdown County Council. The renovation dealt with some accessibility issues. That was why we were the funding party for the project.
Comment on this
The NTA had to pay €753,528, inclusive of VAT. On the face of it, there were only 14 steps. We can see the headline in the media. Only 14 steps cost €753,000. How was that the case? I understand there were accessibility issues. If I had to get 14 steps built at home, it would not cost €753,000.
Comment on this
We do similar at rail stations where there are approximately 18 steps to get to the bridge. Those are the 18 steps that allow people to get to the other platforms. In this case-----
Comment on this
Those steps would not cost €750,000.
Comment on this
By the time you put in lifts and that, it is that kind of price.
Comment on this
No. In the case of the park, this is a project that has cost more than we would have expected.
Comment on this
How much did the NTA expect it to cost?
Comment on this
The initial estimate we were told was approximately €200,000. It went up quite a bit since then.
Comment on this
That is correct. When we became aware of the cost overruns and had a look at the project, it was halfway through construction. It is a beneficial project, in that there is a need to do it. There is a barrier there to people with disabilities.
Comment on this
There was. It was carried out by Dún Laoghaire-Rathdown County Council. It did a procurement process and appointed a designer and contractor.
Comment on this
Did the contractor give the estimate for how much the project would cost?
Comment on this
There are different points to a project. The €200,000 was estimated at the very beginning. At the point they were appointed as the contractor, the estimate was three hundred and something thousand euro. It had gone up a bit. It went up further during construction as various things became apparent.
Comment on this
What were those "various things"?
Comment on this
There were some underground services that were uncharted. They were not on previous maps. They required redesign. There were some-----
Comment on this
Mr. Creegan will appreciate that the general oversight of that project was poor.
Comment on this
I agree that it could have been a whole lot better. We do not manage projects on-site, day by day. They are managed by the local authorities. However, the Deputy is right. There were things that could have been done better in hindsight.
Comment on this
Is there any case similar to that one?
Comment on this
Are any similar cases pending whereby the NTA has put out public procurements, has been given an estimate of the cost at contracting stage and now the project under construction is well over the spending estimate?
Comment on this
We have a portfolio of 1,000 projects. Within that, some projects are well under budget and some projects will exceed their budgets. I do not think there is anything of the scale of this example.
Comment on this
ICT expenditure increased from €5.2 million in 2023 to €6.9 million in 2024. What was that increase?
Comment on this
The primary driver was an increase in hardware and computer software licences. They were brought in to support the relocation to our new headquarters in Haymarket in Smithfield. That was the key driver in the increase of IT costs in 2024. We occupied the Haymarket building in quarter 3 of 2024.
Comment on this
Do the witnesses envisage any other IT issues within the NTA?
Comment on this
There is nothing ongoing within the NTA at the moment. There is no significant IT project that might have a cost overrun in it.
Comment on this
No, not that I am aware of. Last year, we implemented a significant IT-related project, which was to implement a new finance system. That went live on 15 September. It was successful and is in operation. It is in full use through the authority.
Comment on this
Did that project come in within budget?
Comment on this
The witnesses are very welcome. I congratulate Ms Shaw on her appointment. I am a member of the transport committee and look forward to working with her in the coming years.
The work of the NTA in the planning and delivery of public transport infrastructure for Ireland is absolutely crucial to the success of the country, particularly for areas such as my own, Dublin Fingal, which is growing rapidly. That is why the work of the NTA is a focus for me. We need to ensure that the authority is set up for success and has the expertise and competence required, that the governance is to the highest standards and that it really delivers value for taxpayer money.
The train control centre project is crucial to anyone who relies on our rail network. Right now, commuters such as me get frustrated when a DART to Malahide slips in front of a northern commuter line train when I am waiting to go home. I hope this system is going to put in place an efficient logistical, logical, safe and reliable system.
The delivery of it is absolutely essential. However, we need to focus on why it is delayed and why the cost overruns are so large. Following on from the questions already asked, the project was originally budgeted to be €148 million but a portion of that was for the building, which was approximately €40 million. The remainder was to be spent on the ICT software.
Comment on this
What was the budget for the ICT software?
Comment on this
I do not have a detailed breakdown but let us say it was in the region of approximately €30 million. There were other elements of the project too. There were interface works for the signalling system. There was the transitioning of the personnel and training of the personnel on simulators and all of that. There were a number of elements.
Comment on this
If we just focus on the ICT project, Mr. Creegan-----
Comment on this
The project itself, the ICT procurement, was originally procured for-----
Comment on this
It was only for the train management system part, which was the software part.
Comment on this
We are not looking at a 28% overrun there. We are looking at a 110% or 120% overrun if we are looking at a €40 million overrun.
Comment on this
It is the whole package of the project together. Yes, I agree. If you break down the percentages-----
Comment on this
I mean the overrun with the IT contractor, Mr. Creegan.
Comment on this
The percentage of increased payment for the IT element will be higher than the percentage of increased payment for the building and other parts of it, yes.
Comment on this
It will be higher by at least by 100%, by the sounds of it.
Comment on this
It is broadly in that order, I will say, yes.
Comment on this
It is important that Mr. Creegan follows up and sends a letter to the committee with the exact details of the procurement of the IT software. In terms of the actual software, was it to be an off-the-shelf product or was it to be a bespoke product? I am not clear on this.
Comment on this
It is very much a bespoke product. Every railway is different. There is not a big market for selling these systems, as the Deputy can imagine. It is very much bespoke.
Comment on this
At the outset of the project, it would have obviously had a project scope, key milestones and deliverables. How many times since that project scope and key milestones were decided has it been rebaselined?
Comment on this
It has been rebaselined a number of times. I will not give the Deputy an incorrect number but it has been a number of times.
Comment on this
I understand it might be in the region of four times?
Comment on this
It is definitely around that. It could be plus or minus one but that is not a bad number.
Comment on this
It is my understanding that the rebaselining, in large part, was due to the fact that key milestones were not necessarily included in the project scope or the first, second or potentially even the third rebaselining. Am I right in saying that?
Comment on this
Not exactly, no. There was greater clarity on the requirements as time went on. Things changed then because the needs of the railway operator and the rail system became clearer. These are once in a generation type projects. There is no written textbook there with all the detail fully in it. It has to be worked out each time. Yes, there were changes at various points that required the rebaselining the Deputy mentioned.
Comment on this
Going back to my original comments, we need to make sure the NTA has the right experience and the likes of Iarnród Éireann has the right experience and competence to manage these projects. These are really critical and important projects for the development of our public transport system. The whole project leads me to believe that it was not set up for success at the outset. We are looking at over 100% in terms of payments to the ICT supplier. Am I right in saying a large number of personnel within the Iarnród Éireann project management team and within the IT contractor team have had to be changed over the course of the project?
Comment on this
No, I do not think that is correct. There has been augmentation, particularly on the contractor side. It brought in a lot of additional resources but I do not regard that as a change. A lot of the original resources are still there. If you go back to the beginning, because this is so unique as a project, there was an underestimation of the challenge associated with it. There was an underestimation of the time needed. There was an underestimation of the level of granularity that the definition of requirement needed to have. That is now coming to light and giving us many problems.
Comment on this
I have worked on many projects. I am a lawyer and I have worked on many projects. Unless the business and commercial people are very clear at the outset as to what the project is for, what the key deliverables are and what the milestones are, the project is not set up for success. From Mr. Creegan's comment, I think we are agreed on that but it is absolutely essential we learn from this and make sure it does not happen to the other very big IT project - the next generation ticketing, NGT. I understand it is the same ICT supplier and we are looking at a budget of €220 million at a minimum. That is my understanding. This committee needs absolutely confidence that there have been lessons learned and there will not be the same issues, first.
Second, I am at a loss as to how issues with the ICT supplier have led to the State paying over 100% of what was originally contracted with the ICT contractor. Could Mr. Creegan help me with that? Were there any legal safeguards in the State's contract? Did we trigger them? Were we not able to trigger them because we had not included what was necessary in the original project scope?
Comment on this
With Deputy Boland's background, she will know it is all down to the definition of requirements.
Comment on this
In hindsight, the level of granularity of the definition of requirements was not developed enough at the start. Therefore, there had to be more detailed requirements developed while the software was being worked on. That has triggered additional cost. It has triggered additional time. We have implemented a change of approach which is doing it in stages rather than one big bang with all the risks associated with it. The two together have caused us to have these additional increases.
Going back to the Deputy's NGT comment, it is fair to say we were aware of the need to be very specific about our requirements when we were tendering for the NGT project. There was a lot of effort put in during the tendering period to lock down the requirements in a very detailed way. In the work that has been done to date on the NGT project, that has shown itself to be correct.
Comment on this
Good. It is important that this committee is updated on both of these project and that we have clear line of sight as to how they are progressing. The Secretary General of the Department of Transport wrote to this committee before Christmas, indicating the national train control centre project was actually not governed by Circular 14/2021: Arrangements for Oversight of Digital and ICT-related Initiatives in the Civil and Public Service because it was not an IT project. We know the key driver of a €41 million overrun and three years delay is the IT element of this project. If Circular 14/2021 did not apply, what regime applied and did Mr. Creegan get support from the Office of the Government Chief Information Officer and the Office of Government Procurement?
Comment on this
As Irish Rail carried out the development and we oversaw it, I may not have all of the details. That circular the Deputy referenced requires a business case to be developed and it goes through an approval process. There is a separate set of guidelines, the public spending code, which requires a business case to be developed and goes through an approval process. That is what applied in the case of the national train control centre. There were similar things required under those ICT guidelines that were developed for the business case and the approval process it subsequently went through. While the circular might not have applied, the fundamental requirements within it were activated.
Comment on this
Did Iarnród Éireann get support from those offices?
Comment on this
I do not think it did but I cannot swear to that.
Comment on this
I wonder is that part of the reason it was not set up for success?
Comment on this
I do not think so, no. This is such a specialist type of product, a railway train control system, that it is not a skill set you-----
Comment on this
Did we have the competence within the NTA and Iarnród Éireann and do we have it now?
Comment on this
Within the NTA and Irish Rail, the answer is yes. Some of that is resourced in from external sources but, overall, all of the competency requirements are present.
Comment on this
Just to confirm, the next generation ticketing falls within the circular and the Office of the Government Chief Information Officer has been included and the Office of Government Procurement has advised on it?
Comment on this
Full application of that ICT circular applied to NGT.
Comment on this
The witnesses are all very welcome. It is lovely to be here with them this morning.
I will pick up on what Deputy Eoghan Kenny spoke about, that is, the shocking news that broke this morning about the active travel scheme. If time allows, I also hope to ask some questions about the DART+ projects.
We all collectively scoffed at the idea that a bicycle shelter could cost €350,000 and quite often the question came back to why no one said "stop". Why did no one press pause on the project? How on earth can a project to build 14 steps ultimately cost €750,000?
Comment on this
It is a simplistic way of describing it. I understand it says 14 steps, but the reality is there was a gradient issue that separated it. There is a church and community centre on one side and a park and houses on the other side and that route was inaccessible to people in wheelchairs, people with buggies and so on. It required retaining walls, ramps, pedestrian crossings and a pile of other things. It should have been possible to do it more cheaply, but it was still a good project that is delivering good benefits and solved a severance problem that existed there previously.
Comment on this
Did those complexities not arise in the initial application by the local authority to the NTA? I was a councillor for a number of years. The active travel scheme was seen as really important funding that was available to local authorities. Did none of this arise when the local authority applied for the funding in the first instance?
Comment on this
The local authority gave us the concept of the project, which we agreed with, and an estimate. Then it told us the process it would go through to deliver it. That is the normal way we start these types of projects. The estimates at the early stage of a project are based on very limited information. They are rudimentary to say the least. We would have expected some of the things that materialised on site during construction as the project developed to have been found out about during the design phase and dealt with. I have some sympathy about uncharted underground services. They are not on any map, but if we come across them, we have to deal with them. Perhaps some additional trial testing should have been done to find them in advance and such things. There are things that could have been done better that would have reduced the cost.
Comment on this
Was a business case ever presented to the NTA by the local authority for this project?
Comment on this
That size of project does not require a formal business case. We probably would have got some details of what we call a scheme appraisal, which would have given us benefits. Yes, we were provided with some of that.
Comment on this
What is the formal process? Mr. Creegan will correct me. The overall annual active travel scheme fund is somewhere in the region of €350 million.
Comment on this
Okay. This project is looking at €200,000. What is the formal mechanism local authorities utilise to seek funding beyond what was allocated by the NTA?
Comment on this
We have a well developed process, whereby they report to us monthly on any project we are funding. They flag issues that might arise from to time, such as cost, time or something else. In this case, the local authority flagged that a cost issue was arising and there is a process under which local authorities can apply to us. It is called an allocation adjustment request. They apply to us giving us the reasons they need a higher allocation. We have to make a decision about whether to fund it. In this case, we went to look at the site. It was half finished at the time. We think a good outcome will be achieved there ultimately and we decided to provide the additional funding.
Comment on this
How many of those requests were made by the local authority?
Comment on this
I do not know. An allocation adjustment request might be for €10 or €100,000 so I do not have a number. It happens across all local authorities all the time. Sometimes they adjust their allocations downwards because a project is not progressing as fast as was expected and we move the money to another project. It is an ongoing thing so I do not have a number.
Comment on this
Does the NTA ever say "No" to those requests?
Comment on this
Why not say no on a project that has trebled in cost, when there is an alternative entrance that is accessible 50 m down the road?
Comment on this
There are entrances to the park elsewhere, but that road, which is North Avenue, has a 10% gradient. Sending people in wheelchairs down a 10% gradient road for approximately 70 m when they then have to go back up a path in the park is not a realistic alternative. This was and is a good project. It was worth doing. It is a pity it cost as much as it did. If greater care was taken at the design stage, some of the costs could have been taken out.
Comment on this
My frustration stems from having been a councillor in Kildare. There were many projects we would have loved to bring to fruition at a fraction of this price, which would have had a monumental impact. That is a significant amount of money. Would the NTA be willing to share the correspondence between it and the local authority throughout this process so we can see where the responsibility ultimately fell down in this? Will it share that with the Committee of Public Accounts?
Comment on this
A summarised version of it might be more useful than volumes of cost reports and things like that.
Comment on this
Let us say, how many requests came in and at what point certain decisions were made. That would be valuable.
Comment on this
On this specific Deer Park scheme, we will produce a note that sets that out comprehensively.
Comment on this
I thank Mr. Creegan.
Can I get an idea of how much has been spent in total on the DART+ project to date?
Comment on this
It is €512 million. Much of that is for fleet payments.
Comment on this
Does Mr. Creegan have that broken down in percentages of funds associated with external stakeholders, consultancy bodies and so on? There has been a considerable amount in the various different phases.
Comment on this
It is not readily broken down, but there is some synopsis we could do fairly easily.
Comment on this
Okay, if it is available, that would be great.
Has a decision been made on the location of the DART+ West depot yet?
Comment on this
It is our intention that a decision will be announced, or more correctly, that there will be a consultation on a proposed alternative location next month.
Comment on this
Will that be a public consultation?
Comment on this
The last update I saw in media reports is that a Minister from the Kildare North constituency announced that a decision had been made that the depot would be in Kilcock. Can Mr. Creegan confirm that will be the case, or, as he said the NTA is going to public consultation, it is not the case?
Comment on this
The original depot was beside Kilcock, as the Deputy will be aware. If he waits until February, we will announce the proposed location. It is what we and Irish Rail think is the right solution, but we have to go through a public consultation process. It is not that there is a variance in the position. It is just standard practice to go through a public consultation process and take the feedback before a final decision is made.
Comment on this
Is that a statutory consultation?
Comment on this
When does the NTA expect, from the DART+ West perspective, to see the first lot of passengers being able to avail of what will be a phenomenal service?
Comment on this
Realistically, it is about five or six years away, between us getting the DART+ West constructed, the new trains in place, a depot built and the whole thing operational. Construction will start on it next year, but there is a lot of work to do between now and its full delivery.
Comment on this
It is five or six years away for a project that is likely to start construction in 2027.
Comment on this
What is Mr. Creegan's understanding of the status of the south-west project?
Comment on this
The transport sectoral plan says certain works can continue on DART+ South West, such as purchasing land and doing some design work, but the construction under that plan will not start until after 2030. However, there will be a review of the national development plan in two years' time and consideration is being given to whether any other funding avenues could be explored to bring it forward. While the sectoral plan gives one date, I think a lot of effort is going into seeing whether that can be brought forward.
Comment on this
Does Mr. Creegan foresee the construction phase of the south-west project to be likely to have a similar timeframe as the west project? If it starts in 2030, it will not see passengers until 2037 or 2038. Is that reasonable?
Comment on this
No, certain things can be delivered incrementally. What matters to passengers is the new train fleet. They do not really care whether there is an extra track or crossing or such things. We expect to see benefits appearing on DART+ South West a lot earlier than the timeframe the Deputy alluded to.
Comment on this
Is that work contingent on the DART+ West project progressing?
Comment on this
Only part of it is. There is a section of common line so there is an interdependence, but only for part of it.
There are other bits of DART+ South West that could be implemented. There is a four-tracking section that could be implemented and provide benefits in advance of the remainder of the project, and things like that. I am sure that is something that will be looked at in more detail in the coming period.
Comment on this
Gabhaim buíochas le gach uile dhuine atá anseo ón NTA. I appreciate the NTA being here today to go through the issues it is facing with the accounts and its expenditure at local level. I will start with a local issue, namely, the proposal concerning the 425A bus service from [Monivea to ]Athenry. I thank the NTA for carrying out a public consultation on the proposal. The consultation, which closed on Friday, 9 January, was hugely successful in that it engaged a huge number of people in the locality to reflect on the current bus service and consider the NTA proposal. I want to make clear that the proposal to reroute the 425A into Athenry, back out the road to Cussaun Cross and on to Galway city is unacceptable to the people on the Galway road who would lose their direct service to Galway city. It would also increase travel time for people who live further back on the route and use the service to commute to college and Galway city. Athenry is a town with a population in excess of 5,000. It needs its own dedicated bus service to Galway city. As the consultation process has just closed, I do not expect the witnesses to comment on it. When does the NTA anticipate that it will have a report done on the findings?
Comment on this
We are collating the responses we received. It will be a number of weeks. I commit to getting a report together by the end of quarter 1.
Comment on this
Will Mr. Ryan confirm that the plans to reroute the 425A will be paused until such time as the report on the consultation is complete?
Comment on this
That is fair enough. I emphasise that the service is vital for the people who live on that road and they really appreciate it. Over Christmas, many of them used it to travel to Galway and do their Christmas shopping. People use the service to get to college and live their lives. It would be a disaster to reroute the service into Athenry.
I have read many of the submissions made as part of the consultation process. Interestingly, people in Athenry who engaged with the consultation said they do not want the proposed service because they know it would take a service away from other people who live out the road. I believe a dedicated bus service for Athenry would wash its own face and cover its own costs. It is about timings. What made the previous service unviable and led to the private operator pulling out was that the morning and evening services were very busy but the services in the middle of the day were dead. The private operator could not carry it. The PSO obligation has been determined in this regard and we now need to deliver on it. I will happily work with the NTA to make that happen. I appreciate its continuous engagement on the matter.
My next question concerns active travel funding at national level. How does the NTA determine the amount of active travel funding that is allocated to each local authority?
Comment on this
It is based on the projects the local authorities propose. We have ongoing discussions with every single local authority throughout the year. The local authorities put together a set of proposals. As the Deputy will probably know, we have developed a plan in every county, including Galway, for what the network should be. We have to make judgments after that to allocate funding for what we think are the sensible projects in each location.
Comment on this
Does the NTA have a league table? Which local authority is the best for delivering active travel projects at speed?
Comment on this
That is not a winning question to answer. There are lots of good local authorities but I am not sure it would be wise to pick one and say it is a star performer.
Comment on this
The feedback I have been getting from local authorities, in particular Galway County Council, is that when active travel started councils found it easy to draw down the money and tear into projects during the Covid period. The idea of active travel was really welcomed. Then all the gateways were put in place and it now seems that Galway County Council has a number of projects that are in the planning phase. They are being designed and considered but there are no shovels in the ground. I am not seeing projects being delivered tangibly on the ground. For example, the Oranmore active travel project has been talked about for the past two years. It has gone through the planning stage and there have been public consultations. It seems to be never-ending, but maybe a flurry of projects will come to life in the next few years. What performance metrics does the NTA hold local authorities to in order to ensure they draw down the money and perform by getting boots on the ground and making things happen, rather than getting consultants in place to give them reports?
Comment on this
It is a feature in certain places that there is a lot of consultancy support provided and not much delivery on the ground. We are aware of that. We monitor what local authorities are doing. We give them an allocation at the start of the year to do X amount of work on a project. If they are not doing that amount of work, we take the money off them and transfer it to other projects. Sometimes we transfer it within the county because there is something else that is able to progress. In other cases, we transfer it to another county that has a project looking for money in which we are willing to invest.
Comment on this
Between 2021 and 2024, around €1 billion was allocated to active travel. Is that correct?
Comment on this
Galway County Council serves a population of about 190,000 people. I know the money is never distributed on a per capita basis but if Galway County Council had even got 3.75% of the funding over the last few years, it would have received around €39 million. Galway County Council only got about €20 million, which is 50% less funding than it would have got if it was done on a per capita basis. Why did the council draw down or receive less funding?
Comment on this
You cannot allocate active travel on a per capita basis, in my view. You have to have a network that is going to be well used. The reality is that is largely in urban areas and the bigger the urban area, the more likelihood we get useful networks developed. On a per capita basis, you would not dream of installing cycle tracks along rural roads in a one-cyclist-a-day scenario, so we do not do it that way. The logical way to do it is this. We have a network across the country in every county and we work with each of the councils to decide what their priorities are. We then try to distribute the money that is available fairly so that the councils can move on with their priorities.
Comment on this
There are a lot of large towns under the remit of Galway County Council that could drive on projects for active travel. Is it a funding issue, a delivery issue or is it just that all the projects are in the planning phase and we are about to see them come to life?
Comment on this
I think some of it is funding. About three years ago, I would have said we had more funding than we had projects available as people were only getting up the curve as regards knowing how to do them. In the last two years, the situation has changed and we now have far more projects than there is funding available. Therefore, there has to be some level of rationing. Every council would have a similar complaint. They will say they have an ambition to do far more and ask us to please provide more funding, but we cannot do so because we do not have it.
Comment on this
I have conducted a lot of research on purchase orders and payment flow. Does the NTA publish its purchase orders online?
Comment on this
The reason I ask is that Transport Infrastructure Ireland, TII, recently published data in a machine-readable format which covered a huge volume of spend. Does the NTA publish in a machine-readable format?
Comment on this
That is okay. We have had great success with many State bodies publishing in a machine-readable format over the past few years.
I want to ask specifically about one piece of information that was in the TII data. It concerns Turner & Townsend, which is a company I do not know. In the data it appears that approximately €56 million was spent over a period and that the company was a client partner for MetroLink.
The NTA will obviously be heavily involved in MetroLink. How many people are working on or involved in that spend? The witnesses might give me some detail on what is happening there.
Comment on this
TII, with us funding it and with our agreement and support, has engaged a consortium which it calls a client partner - it is really an engineering design team - to do the design work on MetroLink, prepare tender documents and various other things. That was procured about three or four years ago. It has a lot of people working on the project. It varies up and down depending on what stage it is at. When people were preparing for the railway order, it peaked at a certain number. You would have up to 1,000 people working on it at a single time.
Comment on this
There would have been up to 1,000 people working on the planning and tendering. MetroLink is obviously going to be a monster project. It is a huge project, so I accept that everything that would go into that project, from audio to structural engineering to civil engineering, would be massive. It is 1,000 people.
Comment on this
Up to 1,000 people. The same occurred on BusConnects, which had up to 1,000 people. It is important to say that they are not all full-time equivalent people who are there all of the time. They are exactly what the Deputy said. Acoustic engineers are brought in who might take two or three weeks to do something.
Comment on this
They are brought in to do a specific job and that is it.
Comment on this
Exactly, yes. That is the scale of a project like this. They are really big numbers.
Comment on this
I will finish on this. Does the company I referred to manage all of the client partners involved in MetroLink, or how does that work?
Comment on this
That company is the client partner and TII oversees and manages what it is doing, controls the resources it is assigning, etc.
Comment on this
I thank the witnesses for coming in today. I want to raise a few issues with them in relation to BusConnects, especially in regard to how it affects Dublin South-Central. In some ways, the horse has bolted. We have been having meetings on BusConnects for nearly a decade. There are still issues and input from us that I hope the witnesses can consider.
I congratulate Ms Shaw on her new role. Dublin is an old meandering city with a lovely medieval core. It then extends out to Georgian and Victorian districts, while other parts of our city are Edwardian. It is not a grid-like city. We have a lovely historic city and many of the bus routes in the past were meandering, especially in areas of the inner city that I represent, such as the Liberties, Crumlin, Drimnagh, Walkinstown, Ballyfermot, Chapelizod and Inchicore. A lot of the communities in the inner city are connected to communities in Crumlin, Walkinstown and Ballyfermot. That is linked to our housing programme in the 1950s. Many of the communities in the inner city moved out to parts of Walkinstown, Ballyfermot and Drimnagh. For some in the local community, an integral, central part of their week, maybe on a Wednesday or a Saturday, would be to continue to go to the same church or have the same shopping days. The link between the suburbs and the inner city is tangible and real. Imposing a grid system on top of our meandering city has not improved access in many cases. It has disimproved access for a lot of people. They are having longer journey times, reduced reliability, increased walking distances to stops and a loss of direct access to schools, St. James's Hospital, which is a huge one, and the inner city. Those community ties between the old and the new have been really affected.
The 123 bus service is no more and we now have the 122 service. It is a real shame that the 123 service was replaced. It was not just a commuter service but one that functioned as a bus route for children going to school. As part of the development of these urban areas, especially in Crumlin, schools were developed along the same road. There was a bit of thought put into that back in the 1950s. The service came to an abrupt stop, which has caused serious upset for a lot of people, especially elderly people and those with reduced mobility issues. Dublin 12 alone has one of the highest rates of people with disabilities. That is because people want to live near children's hospitals if their child had been diagnosed with a disability. We have a high number of hospitals in the area. Did the NTA formally recognise that the 123 route was heavily used by schoolchildren and elderly people? Was an impact assessment done in regard to school travel? Does the NTA accept that removing the route in this way had unintended consequences for families and people living in the area? I do not know if there is a BusConnects person here. I am grateful for this opportunity because it is very hard for us, as public representatives, to talk to the NTA. It is great to get an audience with the witnesses today.
Comment on this
We do not usually have any issue with elected representatives. I am not quite sure what difficulty the Deputy had. In any case, in relation to the 123 service, the 73 service is a replacement service for the 123 route. It goes to Marino, as well as cross-city. The 122 route was changed at the time of the launch of the 73 service as well to cater for areas that were no longer served by the 123.
More generally on the BusConnects programme, there is certainly a lot of change. Of course, change can be good for some people and not so good for other people. Overall, in relation to the network redesign that we have implemented so far, we are seeing a very positive passenger response. We have seen that in the areas of the city where we introduced the BusConnects network redesign to date, passenger numbers are up by about 30%. That compares to the rest of the network that has not yet had BusConnects, which has had changes of only 6%.
Comment on this
I will stop Mr. Ryan there and ask him generally about another area and bus route, the 80 service. I have been on to the NTA's offices via the Minister in regard to that route. There have been a lot of changes to that route recently. It still is not perfect. Did the NTA do any impact assessment on the change from the 26 service to the 80 service? It is not working for people. We are seeing buses disappearing from live timetables, massive delays, unreliable peak-time services, the phenomenon of ghost buses, missed connections and huge overcrowding. It is really having an impact on people living in Chapelizod and on people commuting into the city. It also has a huge impact on children using the bus. I have been in direct contact with the Minister about this on numerous occasions. I am sure he has been on to BusConnects and the NTA's offices in relation to it. Is there a commitment to properly engage with the community in relation to the 80 bus going through Chapelizod?
Comment on this
The 80 bus service did indeed suffer from teething issues when it was launched. This was for two reasons, namely, driver availability and congestion. There was also some concern, post launch, around connectivity to O'Connell Street. There are connections to O'Connell Street but they require changing on the quays and there are two very frequent services that go to the O'Connell Street area and O'Connell Bridge. As a result, particularly of the congestion issues that the 80 service was experiencing on its new route in an area of the city we had not run buses through before - Bridge Street and on to High Street - we did experience unexpected levels of congestion. We went that way because of the College Green plaza and the plans by Dublin City Council to pedestrianise the area between Trinity College and South Great George's Street. To get to South Great George's Street, which is where the 80 service has to go to get to the southside, we had to use an alternative route. That route was more congested than we expected and delays were larger than we expected.
Subsequent to that, we reviewed the route and, on an interim basis, we are diverting the service along the quays, via O'Connell Bridge and down around Trinity College, Dame Street and South Great George's Street. In advance of the pedestrianisation of the College Green plaza, that is the route it will take.
At a later date, we are planning to-----
Comment on this
I do not mean to interrupt. I have one more question in relation to the DART. The Chair might bear with me as well.
Comment on this
Just one other thing on the 80. In the longer term, we are going to route that service through to Clontarf along the north quays, so it will still go by O'Connell Street. The large majority of people who are currently using the 80 route and who were using the 26 route will have the connections they had in the past.
Comment on this
Okay. I might contact Mr. Ryan's offices again about it for people.
I would like to address the DART+ South West project. I attended the recent opening of the Kylemore town housing development in Cherry Orchard. One of the big selling points is that there will be a station beside it. Obviously, we know now that it has been pushed back to 2030. It is really disappointing for residents there. How does the NTA justify advancing major housing delivery without confirming rail capacity when it is such a selling point to local authorities? In the interim, what public transport guarantees are going to be provided to residents in Cherry Orchard living in the new development?
Comment on this
We do not control housing development as the Deputy is aware. We produce the transport strategy and-----
Comment on this
I know, but they work hand in hand.
Comment on this
I understand. We produce the transport strategy and try to deliver against it, but it is within the funding envelopes that we have been given. Deputy Ardagh said that DART+ South West is commencing post 2030. As I said earlier in response to Deputy Farrelly, the belief is that this will be brought forward. There is a mid-term review of the NDP in 2028. There is an opportunity there to do something.
Comment on this
In the meantime, in advance of the delivery of DART+, we are going to have to ensure we have enough bus capacity there to serve that area in advance. That is the reality of it.
Comment on this
Does Mr. Creegan have any recommendations for us to try to help to get it on the agenda?
Comment on this
It is all about money and it is all about funding, so whatever the Deputy can do on that front is very welcome.
Comment on this
I thank Mr. Creegan very much.
Comment on this
I thank Deputy Ardagh. We will take a short break. The meeting is now suspended for ten or 15 minutes.
Comment on this
I thank everyone for coming in today. I congratulate Ms Shaw on her appointment. Mr. Creegan has been answering lots of the questions. I suppose the next time the authority is in, it might be completely different. At the same time, I totally understand the situation. If they do not mind, I will continue to direct the questions to Mr. Creegan but, obviously, Ms Shaw should feel free to jump in. I do not want to look like I am asking Mr. Creegan while Ms Shaw is sitting there but I know the situation.
Regarding DART+ South West and the DART+ project in general, has it been said that €500 million has been spent on DART+ so far? Is that correct?
Comment on this
It is a lot of money. How is that broken up between the different DART+ projects?
Comment on this
I have the figures in front of me for this.
Comment on this
Within reason, DART+ West is €83 million. DART+ South West, so far, has been €36 million. Fleet accounted for the largest part of it, at €295 million.
Comment on this
What has accounted for the largest part, sorry?
Comment on this
That is the new DART fleet that has been ordered.
Comment on this
That is what I mean. Is that an upfront capital payment?
Comment on this
Exactly. It is upfront milestone payments at the start of the manufacturing process.
Comment on this
It has been paid in a number of tranches since 2022. The first order we did was in December 2022. There has been a number of tranches since then.
Comment on this
Of the €295 million since 2022, roughly how much of that have we received to date?
Comment on this
So far we have three train sets in Ireland, two of which are under tests and the third one is to go, I think, under tests shortly. There are three so far.
Comment on this
It is three train sets. I think they are five carriages long, so 15 carriages. We have to get 275 carriages altogether over the next number of years.
Comment on this
Sorry, Mr. Creegan said, "Three rail sets." Is it three rail sets, and out of how many rail sets is it?
Comment on this
-----a train set on the new DART fleet is ten carriages long. A half-train set is five carriages long. I think we have three full-length trains, which would be 30-----
Comment on this
-----carriages. I think we have. I am not sure if they are full-length or half-length, now that the Deputy asks me. In total, we have 275 carriages to get delivered over the next five years.
Comment on this
That is fine. I was not sure. What was the number for DART+ West?
Comment on this
In this case, there would be property costs because some property was bought-----
Comment on this
There is a capital element to the €83 million as well as------
Comment on this
It is all capital, but part of it could be design costs, Irish Rail-----
Comment on this
Everything is being capitalised. One can capitalise from an accounting perspective. One can capitalise any cost relating to a project. Can we split it into property versus consultants, etc., if we have a way of doing that?
Comment on this
We do. We would have to send that on afterwards; we do not have that information here. There are definitely property, engineering and design costs, site investigations and a host of other things.
Comment on this
There is design and planning. It is a project that has been going on for years. I understand that.
In respect of the €35 million relating to the DART+ South West line, has property been bought? Is that expenditure of a slightly different scale, considering it is a different-----
Comment on this
It is of a different scale. There are fewer properties involved in that particular project. I understand the bulk of that involves design and engineering costs to prepare the railway order and get it through the railway order process.
Comment on this
Now that the DART+ South West project has been put on the backburner, so to speak, is there a risk that we have spent this money and it could be dead money by the time the project is re-engaged?
Comment on this
No. The money spent on DART+ South West was essentially spent to get the railway order. We have the railway order for DART+ South West. There is no life expiry on it, to the best of my recollection. That money was essential in getting approval. That approval now allows us to build this year, next year, in 2030 or whatever year it is.
Comment on this
The project has been put back for a number of years. We do not know when it has been put back to. It has been stated that it is beyond 2030, but who knows what will happen after 2030? How was that decision made compared to other projects? How did that work?
Comment on this
That decision was made in the transport sectoral plan, essentially by the Government.
Comment on this
I might redirect that question to Mr. Ebrill, if that is okay. I thought it might be a question for him or Ms Brady, but I was not sure who would take it. I did not want to be presumptuous. My apologies.
Comment on this
I will take the capital side and Ms Brady the current side. In terms of capital expenditure from 2026 to 2030 under the national development plan published last year, in the order of €12 billion is available for public transport infrastructure across the piece.
Comment on this
I am conscious that I have a ticking clock. I get how much is spent, but how is it decided to spend on one project over another?
Comment on this
We work with the NTA and try to look at the priority projects to proceed. They are MetroLink, BusConnects, DART+-----
Comment on this
I know that. What metrics made that decision happen?
Comment on this
As Mr. Creegan outlined earlier, in order to enable the DART+ programme to proceed, including DART+ South West, we need to prioritise DART+ West because there is a depot component and a track that is shared between DART+ West and South West. Hence, the former got the priority because that project needed to start to unlock the latter.
Comment on this
Within the DART+ programme, the fleet - train carriages - and DART+ West were given a level of priority, informed by the issues I mentioned, namely, it being the unlocker of the other projects.
Comment on this
To clarify, have we bought the fleet for DART+ South West?
Comment on this
There are three orders of fleet that have gone in. The first order is primarily earmarked for the northern line between Dublin and Drogheda, which is very much needed. Those trains will go live next year. The second order will assist the DART in extending to Wicklow, but the final allocation of those trains is yet to be decided. They may go elsewhere. The third order,which went in at the end of last year, is to replace carriages that are 40-odd years old. Further orders will be needed as part of the DART+ programme.
Comment on this
Nothing has been ordered so far for DART+ South West and West.
Comment on this
Further orders will be needed to provide for the full complement. The NTA will have more detail. As the new DART trains enter service on, for example, the northern line, they will free up existing trains to be cascaded elsewhere in the Irish Rail network. That could include the DART+ South West line. That will probably happen from around 2028, I imagine.
Comment on this
That is fine. I get it. I thank Mr. Ebrill. I am just conscious of the time.
On the contactless scheme, why at this stage can we not use a bank card like people do on the London Underground and many other underground train services? Is the technology not there to roll it out? I do not want to be simplistic because I know we are talking about a three-year process. Is there no quick and easy fix? Why do we have to do all of this investigative work, with a cost element to it?
Comment on this
This is something I had experience in prior to coming here.
Comment on this
That is why I looked at Ms Shaw when I asked the question.
Comment on this
The Leap system that we have at the moment works really well. It is an old legacy system and the technology behind that is some 25 years old. It is not able to take the new modern ways of paying through contactless bank cards or phones at this stage.
Comment on this
Is that the Leap card system? It is good enough for the Leap card but not for the-----
Comment on this
The Leap card is a specific card that is topped up with money and the system will take the money off the card, but it requires one to continue putting money on the card through various methods. The new technologies and methods of payment require a substantive change in the system, not just the machines on the street and on board, but also the technology that sits behind it that allows it to talk to the banking system as well as making sure it makes sure the customer gets the right fare deducted from their bank account straight away.
Comment on this
It seems strange. All of us have become so used to using contactless payments on a phone or card. We use one when we go to Lidl, Spar or wherever it might be. Why can the transport service not use something simple like that?
Comment on this
We have an example through the roll-out we have done on some of the buses on the Local Link system. It is a standard transaction. The roll-out allows people to use a bank card or phone on Local Link services, but it is a closed system with a standard one-off fare and new ticket machines were required. We cannot do that on the wider transport system. People change modes and do not use a single mode. A customer needs to be charged the right fare for the type of journey they are taking.
Comment on this
It requires a different set of technology that is a bit more complex and involves payment methods on street and on board and the back office technology that sits behind the scenes working as part of that. A national roll-out would mean making sure every single bus, gate line and Luas stop has the right technology to allow people to pay in that way. When it arrives, it will be transformational in terms of how people pay, but it is a complex project. Following the conversation we had earlier, we need to make sure that the technology is working in the right way and can give confidence to the customer, given that it is taking money out of people accounts. The system needs to be guided and we need to make sure it is safe and secure to do that.
Comment on this
I thank Ms Shaw.
If the Chair does not mind, I will ask one last question, as some of those answers were quite long. We touched on the issue with a previous group. Are bonuses paid to NTA staff?
Comment on this
Our financial statement has a matrix of-----
Comment on this
I went through it and printed out the notes of the financial statement. I thought the figure was quite high. I thought there might be a bonus element, hence I asked the question. My next question is about the average salary. At €89,000, it is quite high. How many staff are there?
Comment on this
The total number of staff at the moment is in the order of 370.
Comment on this
That has increased. I had another question, but I will follow up on that. There are an extra 46 people on the previous year.
Comment on this
I welcome everybody here today. To brief myself, the NTA is responsible for which public services?
Comment on this
It is responsible for providing funding for public transport services on buses, trains and trams.
Comment on this
Is that CIÉ, including Bus Éireann?
Comment on this
It also includes Iarnród Éireann.
Who would be responsible in giving the increases to the CEOs, namely, the €35,000 increase for the CEO of CIÉ, the €50,000 increase for the CEO of Bus Éireann and the €75,000 increase for the CEO of Iarnród Éireann. These are thousands of euro. Who is responsible for that or who would have sanctioned it?
Comment on this
That is not the responsibility of the NTA. I do not know whether colleagues here will be able to answer that question specifically.
Comment on this
I might take that question briefly. To introduce myself, I am the principal officer over public transport governance.
The matter the Deputy is addressing follows on from a review that was undertaken by the Department of public expenditure and reform, which crossed all the commercial semi-State bodies, not just limiting it to public transport companies only. The increases arise from the recommendations of the senior posts remuneration committee, SPRC, review. The committee was established to look at building headroom within senior CEO salaries-----
Comment on this
It was subject to discussion between the Departments of Transport and public expenditure, and the approval of the Minister for public expenditure, Deputy Chambers.
Comment on this
The Minister for public expenditure sanctioned an increase of €35,000 for CIÉ's CEO, €50,000 for Bus Éireann's CEO and €75,000 for the other CEO. I apologise, as I cannot say the word "Iarnród".
Comment on this
That is okay. I just want to know who sanctioned that so I can write to them.
The Leap card free travel for children aged five to eight, if I am correct in that, was very much welcomed. Who is responsible for that area? Is it Mr. Ryan?
Comment on this
Did the NTA make the decision to exclude commercial operators from that scheme? I am from a rural community and we have many rural bus networks that happen there. Free travel for five-to-eight-year-olds on the Leap card free is not available in my area.
Comment on this
The implementation came out of the Government's budget. The Government decided it should be for subsidised public transport services, which the NTA is responsible for.
Comment on this
Subsidised public transport services are all the TFI services.
Comment on this
Nationwide. Is Mr. Ryan telling me that any child aged five to eight who gets on a bus in a rural community like in Monaghan will get free transportation?
Comment on this
Yes, if they are on a TFI-subsidised bus service.
Comment on this
I thought those Leap cards were not working for children to get the free transportation in some rural areas.
Comment on this
If it is a commercial bus service, it is not available.
Comment on this
Is the NTA not discriminating against people who do not have any other services there?
Comment on this
It is not our decision. It is a decision for the commercial operators what fares they charge.
Comment on this
Is the NTA not subsidising the-----
Comment on this
No, we are not subsidising commercial bus operators.
Comment on this
Does Mr. Ryan not think that is discrimination against the rural communities that do not have the services that people have in Dublin?
Comment on this
There are two different types of bus service. There are the subsidised bus services operated by us under public service obligation, and then there are commercial bus services, which operate on a commercial basis. Operators are free to charge whatever fares they wish on those services. We do not regulate those fares.
Comment on this
I have another question regarding the Leap card. Why is the visitor Leap card limited to just the Dublin region? Why is the NTA not expanding that out so that the whole of Ireland is open for tourism and people who come here as tourists can travel right around the whole country?
Comment on this
It has got a set fare on it and the fare reflects the fare you pay to travel around Dublin on a Leap card as a non-visitor. Obviously, we cannot extend that nationwide. Leap-----
Comment on this
Is there no forward thinking about how we would want tourists to travel right around the whole island of Ireland?
Comment on this
The fare would be astronomical if we were to offer-----
Comment on this
Yes, but the NTA could implement different fares and give different reductions.
Comment on this
Is there any plan in place to do that?
Comment on this
At present, Leap products - daily, weekly or monthly offers - are confined to the cities and commuter areas.
Comment on this
It is the people in the rural communities who are not benefiting from this. It is only the people in Dublin who are benefiting from this. We want to have a Leap card all over the country that works for everybody, not just in the city centre.
Comment on this
Well, Leap does work everywhere on our TFI services.
Comment on this
It does not work for the visitors who want to travel right around the country-----
Comment on this
-----and it does not work for the five-to-eight-year-olds who want to get free access to transportation.
Comment on this
Leap cards are available to travel with on all TFI bus services and they offer roughly a 30% discount over cash fares. That is a nationwide offer.
Comment on this
Does the NTA have a vision of what it could offer to incentivise tourists to come to Ireland and use to travel on a network right around the country, including the Six Counties? Is there any kind of vision that the NTA foresees?
Comment on this
The Connecting Ireland programme, which is a rural bus programme we introduced in 2022, has seen a massive increase in rural public transport, which tourists also avail of. We have made changes with tourists in mind in various parts of the country, as well for the local people using the services. We have put a large number of new routes and enhanced services in place over recent years, with 35 last year and 40 the previous year. That programme will continue.
Comment on this
I thank Mr. Ryan.
I read an article about 130 electric buses that were unused for nearly 18 months. Can the witnesses tell me where those electric buses are now and if they are in use?
Comment on this
They are part of the Dublin Bus and Bus Éireann fleets. Dublin Bus has about-----
Comment on this
They are not sitting somewhere in storage.
Comment on this
It was reported to me that they were in storage but that is okay. They are definitely out and in use.
Comment on this
In the interest of being completely transparent, we have further buses to come on stream later this year but the ones the Deputy is referring to have all been in service for about a year and half, I believe, if not more.
Comment on this
Does the NTA have enough chargers now?
Comment on this
We are playing catch-up on chargers. We have extra chargers coming on stream in the next month or so, and more later this year in Dublin and Galway. We do not have enough chargers to electrify the full fleet, so there is a whole programme in place to do that.
Comment on this
The Department of Transport was here with us before Christmas and said that there was a recommendation from the strategic rail review that a rail network would run to County Monaghan. Is that on the witnesses' books or do they have anything on that?
Comment on this
It was always envisaged under the rail review published in 2024 that this was a long-term project. It is not addressed upfront in the national development plan because we are focused on 2026 to 2030. That said, there are a range of investments in the existing rail network that are funded in the national development plan.
Comment on this
The Department has no foresight for Monaghan with the rail network going there yet.
Comment on this
It is in the long-term plans, but it is very much post-2030.
Comment on this
How do we get it into the short-term plans?
Comment on this
That would require additional funding. As we discussed earlier, there are funding constraints. Many projects are funded, but as is the case for all programmes and development plans, not all projects can be funded within one five-year period. However, it is in the long-term plan.
Comment on this
Is there funding in the pot for projects going forward? People in counties Cavan and Monaghan do not have the opportunity to take a rail service to our counties, so we are out the extra money in diesel, petrol and tolls. We have to fork out for all of that. I heard many projects being listed as going to the south of Ireland, but are there projects coming to the north of Ireland?
Comment on this
There are a range of projects. Some are on the current account side if they are new services that have been introduced in recent years, and then there are capital projects in the rail system. For example, we have talked about DART+ in the Dublin area, but there is also the western rail corridor reinstatement, which is funded, the Foyne's line is under development near Limerick, and there is the Cork area commuter rail. There are a range of investments planned across the country. Not all are funded to 2030, but the ones I listed just now are broadly funded to 2030.
Comment on this
How can we get a rail network to County Monaghan funded by 2030? We are disadvantaged again. I brought a map of Ireland in here previously to show the position everywhere north of Dublin. There is no train going to County Monaghan, although there is one to Drogheda and so on. Monaghan has been left out. Monaghan and Cavan have nothing.
Comment on this
We recognise that there is an imbalance in the rail network.
Comment on this
You can see there is a big imbalance if you look at the rail network right around Ireland.
Comment on this
In the north midlands and the north west, many decades ago some rail routes were taken out. The rail review is a strategy to 2050 and it earmarks the reconnection of the north west and the north midlands to the rail network. However, it is absolutely the case, and this was in the rail review, that it will be post 2030. Therefore, it is in the longer term.
Comment on this
I thank the witnesses for being with us today. Given the frequency with which I interact with many of them, I acknowledge the work they do. Given the number of capital projects planned, certainly for my constituency, their work has a very significant impact. Sometimes the impacts are positive and sometimes they are negative. Either way, they all involve public spending. I appreciate the witnesses being here and accounting for the work they do.
I will touch on the metro first. I will direct my questions to the Department first because I am basing them on the 2020 report of the previous Committee of Public Accounts, which contained recommendations dealing with the metro. At that point, we were talking about €150 million between metro north, metro west and the DART interconnector. Whether one uses the word “wasted”, “lost” or “set aside”, for a number of reasons, including a delay and the redesign of the project, it is an incredible amount of money for which we will not see any productivity. In anyone’s book, that would be considered waste.
One of the recommendations in the report was that the Department provide a report on the MetroLink project on an annual basis. I do not know if that has been provided to us. Has it been provided to the committee on an annual basis? Do the witnesses intend to do so?
Comment on this
I am not sure, to be frank. I can check that and come back to the Deputy.
Comment on this
I would appreciate that. A decision was taken before Christmas to establish a specific purpose vehicle or entity. In terms of delivering the metro project, why was that decision taken rather than a decision to invest in either the NTA or TII?
Comment on this
We examined approaches that are applied internationally. There are many different models for delivering major infrastructure projects. There is no perfect model and each has pros and cons, but we and the Minister were of the view that, given the scale and importance of MetroLink and the requirement for genuinely specialist expertise, much of which does not exist on this island because we have never built a metro before, it was appropriate to establish a dedicated delivery body with a dedicated board and sufficient expertise to oversee and challenge the programme. MetroLink-----
Comment on this
Am I correct in saying that body is responsible to the Committee of Public Accounts?
Comment on this
The governance arrangements are being worked through, but that would be the likely case. It would be under the aegis of the Minister for Transport, with a corporate governance relationship in place. A dedicated body-----
Comment on this
Obviously, the Department has responsibility, but it is really important that we have a clear line of sight and that it be accountable to this committee.
Comment on this
That is in our thinking and that is the likely outcome.
Comment on this
These are very large projects. In the appropriation accounts that often come before us, Departments have subheads. Is there any reason a large project such as a metro project would not have a subhead within the Department’s accounts?
Comment on this
I think we are moving towards that. Subheads have been amended for this year, and we see this developing further as the projects move into construction and there is heavier expenditure. We would support that from a transparency perspective.
Comment on this
That may be something we will consider recommending in future reports. We have not seen a project of the scale of the metro project since the Ardnacrusha days. I was at a very impressive market engagement event in DCU. The number of people from across the world interested in the project was what first led me to appreciate its scale. The more transparency there is and the more visibility this committee has, the better. However, we do not want a situation similar to that with the national children’s hospital, in respect of which obtaining transparency is tortuous. Having it from an early stage would stand us in good stead.
My next point is for the NTA. It is great news that we now have clear planning. The public does not have much confidence that this project will ever be delivered. There is huge apathy towards it. A lot of people felt it would never materialise and that it was on the never-never. The reality of the project is going to hit them very quickly. Will Mr. Creegan talk us through the timelines now that the planning is clear, certainly in respect of what we will start to see this year and next year?
Comment on this
There were two big MetroLink developments in 2025. One was to get a very clean railway order. Second, one judicial review has been settled and withdrawn. The project is clear and ready to proceed to construction. I appreciate what the Deputy said in that, in the minds of some members of the public, there may be uncertainty, but those involved in the project are not feeling that. The whole market is gearing up to tender for it.
Comment on this
When will people start to see activity on the ground?
Comment on this
Procurement must occur first. Procurement will commence next month, with the first contract notices out for the big construction contracts. Physical work will start in a big way at the end of next year, and then we will see what the timeline is after that.
Comment on this
Landowners along the route are already being engaged with and there is activity at a very early stage.
Comment on this
There is. There is a lot of activity ongoing. Landowners are being communicated with so they know this is happening, and settlement agreements are being made with all of them because we have to buy property. However, the main focus at the moment is the procurement stage, or procurement for the big contracts.
Comment on this
I urge Mr. Creegan at this point to reconsider the communications strategy. I understand the NTA is in a planning phase and might have a different approach, but during the construction phase, engagement with residents will be absolutely key. At one point, we will be talking about digging a hole the size of Croke Park outside some people’s homes. This will be a very significant project with a massive impact on traffic in my constituency and others. While the goal is great and we want to reach it, we really need dedicated consultation with individual residents and communities on the impact of construction.
Comment on this
I agree 100%. The Deputy is right that, during the planning phase, we were hamstrung regarding how much we could engage with people and say things that were really the subject of An Bord Pleanála’s deliberations. Now we are past that, so there will be a different approach taken. Co-ordination across the projects will matter. There will be three big projects at the same time, namely, MetroLink, DART+ and BusConnects. Co-ordinating across these is our role. We have set up the system to do that. It will have a big part in the next few years as well.
Comment on this
In the time I have available, I might finish on a sour note. We had a very productive meeting before Christmas with public representatives from the Dublin 9 and Dublin 11 areas regarding the roll-out of BusConnects. Both Dublin Bus and the NTA acknowledged that the roll-out had not gone well in the early stages. I have seen a reduction in the number of complaints, but much of this is because people are worn down by the experience. We have only to look at social media – there is a group called Finglas Talks – to see that people are reporting poor experiences nearly every day. I realise there is change proposed for the beginning of February involving the reconnection of the O’Connell Bridge area for the 23 and 24 routes, but we really need to make sure Dublin Bus delivers what was promised by the NTA. There is a challenge in that regard.
Comment on this
We are on schedule for that, the Deputy will be glad to hear. I expect it to be implemented from 8 February onwards.
Comment on this
It is regrettable that what was expected to be a positive development, namely, new bus services, including 24-hour bus services, had such a poor impact. I want to underscore on the record how negative the experience has been, although I realise the witnesses already know this from the meeting. It was an incredibly poor experience for people on the ground, and I believe that is acknowledged on the NTA's side.
Comment on this
We were disappointed with the roll-out and the loss of services that did affect people there, so we do need to see that improve. It will improve over the coming weeks and months.
Comment on this
My constituency will be keeping a close eye on me and Mr. Creegan so that we make sure that happens.
I will finish with this point. I do not know if it has been raised already. I could never understand why it has taken so long to roll out contactless payments, given that every phone in the country has RFID and NFC already installed on it. Surely an app could be built in the space of six or eight months. There are so many apps out there that use RFID technology. Why is it taking so long? Why can we not just build a small app that allows us use the RFID that is in everyone's phones? Why are we loading money onto cards that can be lost? It seems like a crazy system.
Comment on this
It has been covered already but I will respond for the benefit of the Deputy. Obviously the contactless payment system that sits behind the scenes is quite a complex one. As well as rolling out new contactless machines at the stops, at the station gates and on buses, we also need to make sure that the back-office technology works. We will be taking money directly out of people's bank accounts and we need to be able to work appropriately. People will also transfer from one mode to the other so they need to be charged the best value price per day, week, month, etc., as well. That technology in itself is quite extensive. The Leap system is 25 years old and, as a legacy system, it cannot be upgraded to do the kind of thing the Deputy suggests. If only that were the case, we could do things faster. We have to completely replace the old legacy system with the new contactless ticketing system.
Comment on this
Will we have to wait for that to get improvements to the TII app, because that is another legacy issue? People are already using websites like bustimes.org. The TII app is really poor.
Comment on this
We do not need to wait for a contactless system to be in place. There are also things like the new vehicle location system for buses and so on, which will help us upgrade some of the information that is coming on the TII app.
Comment on this
There will be some improvements at some point this year, but we can come back with a bit more detail on that as well. All of what the Deputy just described is not required to wait for the next contactless system.
Comment on this
I have tested the Chairman's patience on the time. I apologise.
Comment on this
I thank all the witnesses for being with us this morning. The National Transport Authority received €1.776 billion in 2024, which is a sizeable sum of public money. It is important that we have this engagement.
As a public representative, I have engaged with the NTA and I am on reasonably good terms with it. It is always reasonably good about coming back, which I appreciate. I have engaged with the NTA over the years and I appreciate the fact that it is accessible in that sense.
I will focus on BusConnects, which is one of the NTA's key projects. I note that in some of the documentation we received that, in the case of Dublin, €239.7 million has been spent to date on BusConnects. What is the comparable figure for BusConnects in Cork? It has not progressed to the same extent as has been the case in Dublin. Do we have a figure for what has been spent to date? What is the overall budget anticipated for the roll-out of BusConnects in Cork?
Comment on this
The spend to date on BusConnects in Cork, which includes depot and infrastructural work, is €75 million. The overall budget has a range of €1.8 billion to €2.3 billion. It is something of that order.
Comment on this
I find the sum of €75 million very high. What are the main components of that expenditure?
Comment on this
We spent €18 million on a new depot. In Tivoli, Bus Éireann is building a depot and we are funding it. That is one part. There has been a lot of the design and development of the bus corridors. We have done certain works to prepare for the new network in terms of putting in turning areas, bus stops and so on.
Comment on this
Bus stops and bus shelters. It seems a high figure. The general sense is that the project is in its infancy, that it has not hit the ground yet or progressed, so to hear €75 million has been spent, I find that is quite high.
Comment on this
It is, but the Deputy must remember that we have to go for planning permission for massively large schemes and they require a big investment to get to the planning stage. It is what we had to do in Dublin and what we will have to do in other cities.
Comment on this
The budget overall is estimated to be about €1.8 billion.
Comment on this
There is a range of €1.8 billion to €2.3 billion.
Comment on this
It is fair to say that there is a lot of frustration with the delays to BusConnects in Cork. What were the original timelines and targets for the project?
Comment on this
If I break it up into parts, there is the infrastructure part and the services part. We completed the design of the services a couple of years ago. The hope was to start rolling out this year, but we needed to build the Tivoli depot before we could roll it out. We will see, but it is likely to be next year before that gets rolled out in earnest.
In terms of the infrastructure, the Deputy is aware of the consultation we went through down there, which was extensive, so it took longer than we expected. We are not in a position to submit planning applications until a piece of legislation is passed that clarifies our statutory power. We are waiting for the legislation to pass later this year. When it is passed, we are in a position to submit the planning applications.
Comment on this
If I could go back to the service part, Mr. Creegan said it is unlikely there will be improvements this year in terms of new services under BusConnects. Is that the case with what I am reading?
Comment on this
Yes. We are in discussions with the Department in regard to new bus services, which includes BusConnects Cork, and therefore we will see later on in the year just when that can commence in earnest.
Comment on this
Cork has suffered from driver availability issues and congestion, which has resulted in issues with the current network that we need to resolve first before we move on to BusConnects' network and design. We want to be confident that the existing services are being run reliably and punctually. As the Deputy is probably well aware, we have been having issues over the last two years in Cork. We are hoping they will be resolved shortly but we cannot be 100% sure they will be resolved.
Comment on this
I am sorry for interrupting but if I could just interject, that brings me to my next main line of questioning, which is the current bus service, and it has aptly been raised. Mr. Ryan will be familiar with the engagement I and other public representatives have had. It has been relentless for the last number of years in terms of complaints we are receiving from the public about the poor reliability of the bus service. There are cancellations of service, late service and inaccurate information on the app. There appears to be no improvement coming through. We have engaged at every possible level with Bus Éireann, the National Transport Authority and we have raised it in the Dáil, but it still seems there is little or no light at the end of the tunnel in terms of providing a bus service that is a reliable, modern part of a public transport system in the Cork region. Is that a fair description?
Comment on this
It has been difficult over the last couple of years. We do see some light at the end of the tunnel. Bus Éireann is now recruiting internationally and it paid a visit to South Africa before Christmas. It had a successful engagement with drivers there. It is looking at bringing in 40 drivers initially and more as the network redesign rolls out.
Comment on this
We have been hearing about driver recruitment for a couple of years now. The most recent update I got was that progress was being made, the numbers have improved, and so on, but it still appears to be the main reason or excuse for the poor bus service people are experiencing. When will this issue be resolved?
Comment on this
As I say, we are earnestly hoping that the recruitment of drivers internationally will resolve it. There has certainly been a driver shortage in Cork, which is not unique in this regard, since Covid. It has stopped us doing what we wanted to do in Dublin as fast as we wanted in terms of the roll-out of the network redesign. It is obviously impacting on existing services as well from time to time. It is fair to say that Cork has been particularly badly hit.
It is not the only reason. The other issue in Cork is congestion. There is a significant lack of bus priority in Cork compared with other cities, in particular Dublin.
In order to be able to just keep up with what we are currently providing, we have to put in additional funding each year just to keep the show on the road because journey times are reduced and we have to put more buses and drivers out there to maintain the current service level. That is a difficulty as well. Last year nationwide, we spent €9 million just to keep the show on the road, with no additional services.
Comment on this
What assurance can we get today about a better service in the foreseeable future?
Comment on this
As I said, we and Bus Éireann believe the driver recruitment will resolve the issue in Cork. A period will be required to arrange visas, accommodation and so forth for those drivers.
Comment on this
Yes, Bus Éireann is actively planning for this now.
Comment on this
That is for new buses or a new fleet for the additional drivers that will be recruited. Is there funding in place?
Comment on this
They are to drive the existing buses. We are not talking about a new fleet.
Comment on this
The main issue remains driver shortage.
Comment on this
The main issue as regards existing services is driver shortage but congestion is a significant issue as well.
Comment on this
On that and the penalties imposed on Bus Éireann, Mr. Ryan mentioned earlier that Cork is particularly bad and I completely agree. The Department of Transport was here recently. I looked for figures, which we are still due to get. Can any of the witnesses inform me what penalties have been imposed on Bus Éireann for its poor service delivery in the bus network in Cork?
Comment on this
With the way our contracts work, it is a difficult question to answer. The contract we have with Bus Éireann is across the country. Cork is one element of that. We apply various deductions depending on whether the bus runs and whether it runs punctually and there is an element of service quality assessment as well around whether-----
Comment on this
Therefore, we do not have a figure.
Comment on this
We do not have a number. It is a difficult number to provide.
Comment on this
Okay, I will ask the Department of Transport to provide it. I will move on.
Under active travel, I will home in on one particular issue, namely, pedestrian safety on pedestrian crossings. I noticed in my area recently that many of the new pedestrian crossings have raised platforms, which I completely agree with. It is an additional safety measure. Is that an NTA design standard now for pedestrian crossings?
Comment on this
It is not a mandatory requirement, but it is the design most people go to now for pedestrian crossings. Not all disability groups appreciate it, I should say, so there are places it would not be done, but in a lot of places, it is the solution that is put in place.
Comment on this
I would expect it to be accessible to people with disabilities if it is designed appropriately.
Comment on this
The disability groups' issue is that the vision impaired do not see the transition from footpath to carriageway as clearly as they would like. They have a concern on that front.
Comment on this
Okay. The other side of that is retrofitting existing crossings. Can that be looked at, in terms of providing funding? The safety of pedestrian crossings, especially on busy road networks is a significant issue that comes up for us as public representatives.
Comment on this
We have done plenty of those. If Cork city or county council has proposals, we will certainly look at them.
Comment on this
I will turn to transport security. It is provided for in the programme for Government. I take the train from Cork to Dublin and see some security. When I take the Luas, I see some security, but I do not see it anywhere else on public transport. I do not see it on buses, for example, or elsewhere. What is the plan or vision for transport security?
Comment on this
I might take that question from the Department's perspective. The Deputy is absolutely right that there is an operator-wide approach at the moment, which applies to each different mode of transport. The Department is actively working on putting together the initial plans for the transport security force. The Minister is absolutely laser-focused on that as well. We are looking to finalise the organisational model particularly, that is, how the security force will sit under the remit of the NTA and then also look at what kind of primary legislation will be required to implement that organisational model and give requisite powers. We are also looking at contracting arrangements and so forth. The Minister hopes to have an update on that in the coming weeks.
Comment on this
I thank all the witnesses and I congratulate Ms Shaw on taking on her position. I think she said at the infrastructure committee that she had been here three and half weeks so she is now approximately 50 days into the job by my calculation. Was she aware before this meeting of the whole Dún Laoghaire-Rathdown €750,000 step debacle? What is her knowledge of it or what had she been told about it?
Comment on this
As the Deputy can imagine, I was briefed on the issue ahead of this committee meeting and as part of the wider programme and I have also been reading the reports in the local press about it.
Comment on this
What is Ms Shaw's instinctive reply to what has happened?
Comment on this
It goes back to what Mr. Creegan said earlier. At the early stages of a project, people come with an estimate of what they think is required. As the project matures, they have more information, which will give more certainty about what needs to be constructed, what the agreed scope is and what risks are associated with the delivery of the project, such as ground conditions and utilities, which have been cited in this. That should then inform a more detailed design, which would give a more robust figure for what is required for construction. Some of the events here happened during construction. Should some of those things been known about beforehand? It is not always possible to know those things. Most projects will come across something when on site, which need to be managed. What people normally do is a lessons learned from that whole exercise, working with all parties who were involved - the project was delivered by the local authority - and then take that learning and make sure it is disseminated to all the other organisations that are delivering similar projects.
Comment on this
I presume Ms Shaw had a gut instinct. She is a very experienced person from working in the west midlands. She must have some sort of gut instinct when she heard the NTA had spent €750,000 on 14 steps and a ramp and that it had given that money to a local authority. As the new sheriff in town, she came into the organisation. When it emerged the OPW had spent all this money on a bicycle shed, the new person came in and looked under the bonnet. When he came before the committee, it was sackcloth and ashes. It was extraordinary, terrible and awful. We are not hearing that same language about this project. That is what I am trying to get from Ms Shaw. She has a fresh start. Something clearly went wrong here. The public is aghast at the idea that the NTA would spend €750,000 on 14 steps and a ramp, whatever the circumstances might be. Does Ms Shaw accept that?
Comment on this
My instinct having arrived - I have been here for eight weeks now - is that something on the project led to the occurrence of this particularly large cost overrun. It is a case of understanding all the make-up. It was not a simple project. The site conditions, the gradient and an additional controlled pedestrian crossing added to the costs, so there was an increase in the scope. Site conditions, utilities - what was under the ground - and all those things, could they have been predicted beforehand? Probably. Do we need to make sure we are more robust in doing the cost estimates? There will always be a difference between an initial cost estimate from an outline concept and the business case, or in this case the appraisal, of the project with more certainty around a more detailed design. However, we have to deal with the things that occur on site that it was possible to anticipate and make sure the risk registers of these projects are robustly managed as part of it.
Comment on this
The challenge with an issue like this, which relative to the budget the NTA spends is a trifling amount of money, is that it cuts through to the public. It lands on Ms Shaw's desk as CEO. It is her responsibility to uphold the credibility of the organisation of the NTA and this issue has now undermined how the public views the NTA. We cannot speculate about the extent of how that will go. The OPW suffered real reputational damage from the bicycle shed. As regards lessons learned, what can be demonstrated to the public in terms of what is new, what changes will be made, so that, particularly in the active travel budget, this is not symptomatic of governance control failures in how the NTA funds local authorities for projects?
Comment on this
I have worked in public service my whole career. I am motivated about how public money is spent and making every cent and euro count in every project I am responsible for but ultimately about also delivering outcomes for people. In this case, as Mr. Creegan said, this project is absolutely worthy of delivery in terms of accessibility for people with wheelchairs, pushchairs and so forth to the church and park, with a safe crossing point, as well as being able to move around. If we are motivated by those outcomes, it is about making sure we have the right processes in place and are working collaboratively.
These are projects that are delivered by local authorities. How do we make sure that local authorities have the right capacity and capability? We have provided, through some of the measures we have taken, access to expertise through the framework contracts that we have for consultancies, etc., in circumstances where local authorities might not have full capacity in order to help them deal with those upfront and more robust costs of analysis.
Comment on this
Is there a problem with the funding structure? In the example we are discussing, the local authority went out to contract, got an estimate and got funding approval from the NTA. When it emerged that more money was needed, it went back to mummy and daddy in the NTA and said "Show us the cash". The NTA carried out an inspection. It all falls back on the NTA, even though it is the local authority that is managing the projects. Should a firmer line be taken where the NTA would say "Sorry lads, you looked for €250,000. Find it from within your own budget if you want to proceed with that project"? How can we have prudent financial management if every time there are project overruns, local authorities go back to mummy and daddy and get more money? That is a problem, is it not?
Comment on this
That is an absolute consideration when we are looking at some of these cases. When the full appraisal and final design before construction were entered into - I think Mr. Creegan mentioned this - the project value was €300,000. That was the cost we were tracking, as opposed to the €200,000 at the very beginning. As it is on site - and I do not know how much of the delivery has been undertaken - it is more dangerous to pause a project because when one is in contract with a supplier to build something, one just incurs more costs while delaying a decision on how one will fund that project. Delivering the project was probably a consideration when the team was deciding to fund it in full. All that has to be taken into consideration. I do not know the full depth of all the circumstances in this particular case but the Deputy is absolutely right. For me, in the context of coming into the organisation and making sure we have got the right structures in place and supporting the local authorities to be more robust about cost controls, contract management and delivery-----
Comment on this
Is that something Ms Shaw will prioritise to review, particularly as she said she did not know the full circumstances?
Comment on this
Certainly, working with the team that is responsible for the capital delivery and supporting the local authorities, we do need to look at it and make sure that lessons are learned from this particular example. We are helping to communicate that to other local authorities. We are already helping to build capacity and capability through some of the frameworks we have put in place for access to the right level of resources. More robust design and more robust cost estimates and contract management are part of it as well.
Comment on this
The issue of ghost buses is a permanent one. Lots of people have raised it. How does the financial penalty mechanism work? Dublin Bus was hit with whopper amounts in terms of its contract - I think it was €7 million in 2023 - and there are other companies like Bus Éireann. For the private entity Go-Ahead, there is a clear impact on its bottom line. It is going to lose €200 million of the money it was going to get. Is taking money from Dublin Bus, Bus Éireann, etc., working in the context of trying to deliver a better bus service? Are we not just running around in a circle in this regard, particularly as these companies still need drivers and maintenance staff? What is the function of that deduction? Is it having any effect at all?
Comment on this
We believe it is. In our direct award contracts with the CIÉ operators, there is a line item relating to reasonable profit. This is an amount that the operators are allowed to keep under European regulations in relation to subsidised public transport direct award contracts over and above the cost of running the service. However, it is affected if there are deductions imposed. That profit would be eaten away. As a result, there can be occasions when they end up with little or no profit at the end of a year. We do believe that this is a motivating factor for Bus Éireann and Dublin Bus.
Comment on this
We will still harangue the NTA, however, and ask where the buses and drivers are and why are buses not being maintained? The NTA is going to go to the Minister or whatever. It is difficult to discern how deducting money from them works when they will find other ways to get money, particularly in circumstances where we want a functioning service. I understand it perfectly on the private side – it hits their bottom line, so there is a clear driving force.
Comment on this
No. As I say, the profit will be taken away from them, in whole or in part, depending on how well they perform during the year. This will be done by means of deductions.
Comment on this
They will come looking for the money some other way.
Comment on this
And then we will have a crap bus service.
Comment on this
There is no mechanism to give them a reasonable profit above and beyond what is in the contract.
Comment on this
Mr. Ryan can see the circular argument I am making. I am sure I am not the first person to make it.
Comment on this
I do understand to some extent. I accept that in relation to what we call directly awarded contracts to internal operators, it is a bit of an issue.
Comment on this
I will finish on this point. It relates to people's frustration. In the context of the high-frequency bus services that work, passengers absolutely love them. They are voting with their feet. Those services are fantastic. When we deliver a new high-frequency service that does not work, however, it completely undermines confidence in bus services. When this happens, all the new passengers that the NTA is hoping to get will either never materialise or it will take forever for them to do so. That has to be taken into consideration a lot more than has been the case to date.
Comment on this
I thank the witnesses for attending and for their presentation. I also want to start with the issue of buses. One of the things that is interesting from the NTA figures is that they confirm anecdotal evidence to the effect that Go-Ahead is significantly worse than Dublin Bus. The buses I hear most about - apart from the F spine, which is a new addition - are the S6, S8, W6 and the W2. Those are where people are left waiting at bus stops and ghost buses. There is an Instagram account called @ihatethes6. Things are that bad. The national figures confirm that by every metric of reliability, punctuality and penalties incurred, Go-Ahead is worse than Dublin Bus. Go-Ahead incurred 22% of the fines for buses in Dublin in 2024 but provides only 12% of the services in terms of passenger journeys and is responsible for only 17% of vehicle kilometres. Is it accurate to say that, on average, Go-Ahead is worse, less reliable, less punctual and so on than Dublin Bus?
Comment on this
Not on a like-for-like basis. What we need to understand is that there are two different types of contracts. In the case of the Go-Ahead contract, deductions can be higher than they are in direct award contracts. In the commercial contracts we have higher deductions and also incentive payments if they are doing well than is the case in direct award contracts. The other thing to note in relation to Go-Ahead in Dublin in particular is that since the network redesign was rolled out, it has taken on a significant number of orbital routes on which congestion is quite severe. As a result, punctuality is much more difficult to achieve than where there is a radial route or, in many cases, a bus corridor in place. It can be a more difficult operating environment for Go-Ahead. Having said that, after the Go-Ahead contract was first introduced in 2018, we did see a significant improvement in performance on routes which Dublin Bus had operated in the past and which Go-Ahead took over. Although there are undoubted challenges in relation to congestion and driver availability from time to time, as there are with all operators, we believe Go-Ahead is doing a good job.
Comment on this
The NTA’s figures suggest that Dublin Bus is much more reliable and more punctual than Go-Ahead. Mr. Ryan is saying that there are different routes, but I assume that the targets take into account whether they are radial routes. I do not see why it is fair that because a route happens to be run by Go-Ahead, commuters seem to get a worse service as a consequence.
Comment on this
The service is a product of both the operator and the environment it is operating in. As I said, in the case of several new routes Go-Ahead has operated or taken on as part of the network redesign, the operating environment is not ideal, particularly towards the end of the year when traffic congestion is particularly bad, namely in October, November and the lead-up to Christmas. It is much more difficult to operate in an environment where there is no bus priority than where there is.
Comment on this
I know bus drivers who work for both Go-Ahead and Dublin Bus.
They tell me that the fundamental difference is that Go-Ahead Ireland has a harder time retaining staff. It is not so much that it offers poorer wages but that it offers poorer terms and conditions. It offers worse shifts for drivers. People get trained up by Go-Ahead Ireland and then move somewhere else. That is a consequence of the competitive tendering process that the NTA has set up. It is not its political decision, but the basis on which these companies compete is on punctuality and so on, and the costs involved. I do not see that this model of competitive tendering has delivered for people.
Comment on this
There are times when Dublin Bus has driver availability issues. There are times when Go-Ahead Ireland has driver issues. There are times when Bus Éireann has driver issues. Dublin Bus had significant issues with driver availability in the summer and dropped a lot of kilometres because there were driver shortages in the summer. From time to time, the same thing happens to Go-Ahead Ireland. Does it happen more to Go-Ahead Ireland than to Dublin Bus? Not really. Over time, it does not.
Comment on this
I would be interested to see the figures in that regard. Related to that is the issue of the key performance indicators, KPIs. Bus drivers tell me that the KPIs set by the NTA effectively incentivise ghost buses. You are penalised if you are more than one minute ahead of time or more than six minutes behind. Bus drivers are under an incentive to slow down if they are making good progress. You might be slowing down on the first part of your route in order to make sure you are not ahead of time. Then you hit traffic and, all of a sudden, you are more than six minutes behind. You cannot just get around the traffic. You can slow down but you cannot necessarily speed up. What happens then is that there is an incentive to become a ghost bus and not pick up anyone else. You can cancel the service on the basis of traffic-----
Comment on this
Does the Deputy mean you can skip stops or curtail-----
Comment on this
-----of traffic congestion. In the way the KPIs are set up, there is effectively an incentive to do that.
Comment on this
If services are cut short or do not operate at all, there are obviously deductions in the contract. We see the data. If a bus has not run the full length of its route, we see there is a gap in the data versus the scheduled data and we can deduct payments from the operator for the service not operated. We have that transparency.
Comment on this
Are operators punished more for late buses or for cancelling buses? What happens when a bus does half its route?
Comment on this
In the case of the lost kilometres from cancelled services, we deduct the cost to the operator of operating the service if it is within its control.
Comment on this
It is not in the operator's control if the issue is traffic. That is what the operators are saying.
Comment on this
There is a grey area. There is a lot of debate at times. We have a cost code that we allow operators to use for abnormal traffic congestion.
Comment on this
We enter discussions with operators on various occasions about what abnormal means. We do look for some evidence that it is unusual and out of the ordinary, as opposed to something that it could timetable for.
Comment on this
That is precisely what bus drivers tell me. They are under an incentive from their companies, whether it is Dublin Bus or Go-Ahead Ireland, to say there is abnormal traffic and to cancel the route. As a bus driver, you would prefer your bus to arrive ten minutes late than not to arrive at all.
Comment on this
It is our job to pick those up and to query them with the operator.
Comment on this
The drivers say that, as currently structured, the KPIs are incentivising that.
I will move on to the issue of taxi regulation. Do the witnesses think that the model of NTA taxi regulation, whereby a maximum fare is set after a process of consultation, and the economic environment and what is affordable for people are considered, along with what is decent for the drivers, is being undermined by the app companies at two levels? On the one hand, Uber used a fixed-fare model that undercuts the agreed fare. That could potentially make being a taxi driver a very unstable career and could, therefore, undermine our taxi industry. Uber does that in order to capture market share and will hike up prices later. There is also the issue of the utilisation of these technology fees, which are €9 in some cases. As far as I understand, those fees sit outside the maximum fare regulation. An app company can say it is completely abiding by the maximum fare regulation but is adding an extra €9, which can become €10, €15 or €20. Is our model of taxi fare regulation being undermined? Does it need to be updated?
Comment on this
There is some work being done with the Department to look at the taxi regulations, particularly in terms of the dispatchers, to see whether there needs to be additionality in how they are regulated. The work to do that is now under way and should help. The technology charges will also be incorporated in that review. We are here to regulate the taxi vehicles and the Garda does the taxi drivers. It is a commercial decision between drivers and whoever they are driving for to make sure they are doing that.
As has already been stated, I have only been here for eight weeks. In respect of taxi regulation, I can already see some of the benefits of having a maximum fare imposed. I have not seen that elsewhere. That is good for the consumer and the customer who is trying to use the taxi. Our requirements are to ensure that taxi services are available for people to use at the best price. We are looking at reviewing those regulations.
Comment on this
Would the NTA consider the introduction of a not-for-profit app run by the NTA? Companies such as Uber make billions. It is huge money, and for what? Uber has produced this algorithm, but all the work is being done by taxi drivers. In a sense, the taxi rank, updated to today, is a taxi app. Is that something the NTA would consider?
Comment on this
We have to consider all options to decide which is the best provision with the regulations for which we are responsible. We do not cover all the regulations around taxi services. We must look at all options as part of the work we do to review the dispatchers.
Comment on this
On electric buses, there was a question about a particular cohort of buses and whether they are in use. Mr. Creegan said they were, but qualified that to clarify that he was not necessarily saying that all the buses are in use. Are there any electric buses currently not in use and sitting idle, and, if so, how many?
Comment on this
We have an order in with a manufacturer to manufacture buses. That is Bamford Bus Company in Northern Ireland which runs Wrightbus. Approximately 130 buses are coming through under that order. They will be distributed across depots later this year. They have still to come on stream.
Comment on this
They may become idle.
Comment on this
It is my expectation that they will all be deployed later this year.
Comment on this
No electric buses are currently idle in bus depots.
Comment on this
Some of those 130 buses have been manufactured and we have not taken them into the fleet yet.
Comment on this
Are all electric buses in the fleet in active use?
Comment on this
I do not want to say that every bus is. There are single-deck buses and not all are in active use, but more will come into active use in the months ahead. They are all ready to go into active use. Let me put it like that.
Comment on this
Could Mr. Creegan get, and send to the committee, the figure for how many electric buses that are currently in the fleet are not in active use? There are various estimates from people online who seem to know these things and who seem to think a lot of electric buses are not in use.
Comment on this
We will get the Deputy the correct figure.
Comment on this
I thank Mr. Creegan.
Comment on this
I will pick up on some local issues to start. I will focus on rail infrastructure in Drogheda. The new northside train station is a key objective of Louth County Council's development plan. It has been an aspiration for over two decades. It appeared in new development housing brochures as far back as 20 years ago. Many people from Dublin city centre bought houses in Drogheda and moved to the areas in close proximity to the new proposed train station, with a view to commuting to and from work and social engagements with ease. Unfortunately, they are still waiting and their houses prices have plummeted and whatnot.
I raised the issue at this committee in November. Mr. Garret Doocey of the Department of Transport said:
The future location of a potential train station on the north side of Drogheda will be looked at in the context of engagement between the NTA and Iarnród Éireann as regards priorities for funding over the next couple of years.
It came as a bitter disappointment that subsequently, there was no reference to, or mention of, this long-awaited infrastructure in recent announcements relating to the €24 billion national transport and sector investment plan published in December as part of the national development plan review. In fact, the only single reference to Drogheda in the whole plan was a vague reference to potential works, not even confirmed works, on a new platform at the current MacBride railway station in Drogheda to make way for the DART+ Coastal North extension before 2030, which is just a rehash of a previously announced project that is already a year behind.
For those who are not familiar with Drogheda, it is the largest town in the country and is projected to become the next city in Ireland. It is already meeting the metrics of city status by population, with in excess of 50,000 people living there. The population is set to grow by 20,000 in the coming years as a result of massive housing development on the north side of Drogheda, where the aforementioned train station is located. That development, combined with supporting infrastructure, including a new IDA Ireland park and new sporting and amenity facilities planned for the area, means that this north-side train station is needed more than ever. With all of that in mind, what engagement or communication has the NTA had with Irish Rail, Louth County Council and the Department of Transport? The Department seemed to suggest that there was some engagement going on behind the scenes. Can the NTA commit to reviewing the matter this year, with the possibility of coming back to us with further information on it?
Comment on this
Because that location is in Louth, it falls outside our statutory remit in terms of rail infrastructure. It is not part of the greater Dublin area transport strategy, so we have not looked at it closely yet. It is something we could look at with the Department and Irish Rail in terms of the logic or concept but it is not provided for, funding wise, in the current sectoral transport plan. In terms of getting a start and looking at it, between ourselves, Irish Rail and the Department, that could be picked up. I am not sure about later this year but certainly next year could be a target in terms of looking at that, to see what the feasibility is-----
Comment on this
To Mr. Creegan's knowledge, none of this is going on already with the NTA.
Comment on this
No. I can say that it is not going ahead because it is outside our statutory remit at the moment.
Comment on this
That is fair enough. We might revisit that the next time the witnesses appear before us. Sticking with rail infrastructure, the first batch of 65 battery electric train carriages are expected to enter service on the Dublin to Drogheda line in 2026. I have received correspondence on this from constituents and other interested parties who are asking how fast these DART trains travel in comparison to the Belfast Enterprise or regular commuter trains. To be honest, I do not know much about it but there seems to be a fear that they do reach the same speeds as the Enterprise and this may lead to congestion or jams on rail lines. Does the NTA have any concerns in that regard?
Comment on this
The trains comprising the new DART fleet have a maximum speed of 140 km/h to 145 km/h. While I am not familiar with the speed of the Enterprise, I would imagine it is no more than that. The issue is not the maximum speed that the vehicles can reach but the stopping patterns that are going to operate on the line. There is a long-distance, intercity Enterprise service which must share the line with the commuter services. Timetabling that to work effectively on a twin-track line, which this is, can be challenging. The speed of the trains or the capability of the DART fleet is definitely not the issue. They are more than capable of any speed we would want on that line. The issue is the stopping patterns we ultimately have to operate to integrate Enterprise, DART and whatever else is on the line.
Comment on this
Does that explain the need for the new platform at the existing station? Is that to alleviate-----
Comment on this
No, the new platform at Drogheda station is to do with the charging of the new fleet. We want to be able to charge two trains at a time. As a result, we needed a second platform to be able to stack a second train there for charging purposes. That is what it is required for.
Comment on this
In relation to park-and-ride facilities, I know there are strategic locations outside the main cities. The focus is currently on the N11 corridor and the M1 corridor at Swords. In terms of my initial comments about my hometown being a commuter town thanks to Government policies, the same is true of many of the towns surrounding our large cities and all of them are crying out for park-and-ride facilities. Is work being done in the background by the NTA to develop more such facilities, specifically around Drogheda?
Comment on this
On that broad corridor, we have planned a strategic park-and-ride facility but it is down further south, at the Lissenhall junction on the M1. We are trying to capture people coming from the Drogheda area who can transfer to public transport just north of Swords. There is a planning application with Fingal County Council for a large park-and-ride facility, with 1,000 spaces, near Lissenhall junction on the M1. In time, that transition to a 3,000 space park-and-ride facility for the Metrolink service which allow people to interchange there. That is the focus on that corridor in terms of the strategic park-and-ride location north of Swords at Lissenhall.
Comment on this
Yes, but with respect, that is a 30- to 40-minute drive from Drogheda. I am raising this because on the main roundabout onto the M1 coming from the north side of Drogheda there is a retail park with Woodies, Tesco, Lidl and so on, which is an unofficial park-and-ride facility. People are parking their cars or car pooling there, just off the motorway. There is massive development going on, with the whole area being choked by infrastructure at the moment, including road and transport infrastructure. It is leading to congestion around the whole area, particularly at peak times in the mornings and evenings when people are going to or returning from work. That is starting to affect shopping in the retail parks by people in the new housing developments that have been built in the area. If the witnesses take anything from here today, it should be that there is a need for a park-and-ride facility in Drogheda near the motorway, either north or south of the town. The north side would be preferable because that is where the problem of choking congestion is at the moment. I urge the witnesses to take that on board and consider it seriously. The situation will lead to accidents and is already having an effect on trade, the economy and housing.
Comment on this
What the Deputy is talking about is a level of park and ride below the strategic one that I just spoke about. It would be more local or semi-regional in nature. We have done a couple of those with Meath County Council in particular, which have been very successful, where there were patterns of people parking up at the side of the road and so on to get a bus service. The council took the lead on that. What the Deputy is talking about are more local park-and-ride sites. If Louth County Council wants to take a look at that and propose something, we will certainly talk to it. It is a local park-and-ride site to mop up usage that seems to be occurring there, from what the Deputy is saying in any event.
Comment on this
I appreciate that. My final comment on that is that I would not underestimate the level of usage that would be involved there. I have already referenced the population and the boom that is to come with the development of housing, amenities and infrastructure, all of which is planned and in the making as we speak. That usage and demand is only going to grow as time goes on. I will certainly take that point back to the councillors in Louth. This is an issue that they have been raising themselves in recent weeks at their municipal district meetings. If we do see something like that coming in, it is important that we do not underestimate the need. It is crucial to unleashing the potential of the area.
Comment on this
I have a few questions. Before I ask them, I congratulate Ms Shaw on her recent appointment and thank her coming in and engaging with us today. I also want to thank the NTA for the plethora of responses to parliamentary questions that I have received in recent days, although I would point out that they were with authority since September of last year. I know there are issues with capacity but perhaps that can be looked at, in order to ensure all Members get relevant information as quickly as possible. Again, thanks for the plethora of responses. I am not sure whether they arrived because the witnesses were coming before the committee today or whether they were just stuck in an out box..
My first question relates to DART + and the rail carriages. I ask the witnesses to talk me through that. As I understand it, the initial order was submitted in 2022. Is that correct?
Comment on this
That was for 95 vehicles. We describe them as 19 half-train sets.
Comment on this
They were expected to go into service at the start of this year.
Comment on this
They were expected to go into service in 2026 but what was the delivery time? Obviously, there are lead-in times and so on.
Comment on this
There is no single date. They are delivered incrementally over a period of time because they are big pieces of kit. The first one was due early last year and I think it came in fairly close or a little bit later than the planned date. We have three trains here already, so the deliveries have started.
Comment on this
Three trains have been delivered. That is about 30 carriages, as Mr. Creegan alluded to earlier on. Should all 95 carriages have been delivered at this stage?
Comment on this
At the time of placement of the order, the expectation was that we would have all the carriages at this stage.
Comment on this
The manufacturer had a couple of difficulties. The two biggest ones were to do with batteries on the fleet. The decision to change the battery type from what the manufacturer originally offered to a revised battery type was based on something that happened in Melbourne, Australia. The manufacturer had other issues, all of which are technical. Another one was that the friction material in the brake pads did not perform correctly and they all had to be changed.
Comment on this
The failure to honour the contract has had bigger repercussions in the delivery of service on the Drogheda to Dublin line, but there were also knock-on impacts even in my own constituency of Wicklow as the expansion of the DART service as far as Wicklow town has been affected. What financial penalties, if any, were in the contract?
Comment on this
I am not sure that the first fleet order affected the Wicklow project. The second fleet order was going to provide the train sets to get to Wicklow.
Comment on this
It did have a knock-on impact and I am going to touch on that in a moment. Will Mr. Creegan comment on the financial penalties or the nature of the contract?
Comment on this
It is what is called a framework contract. It is a contract that extends over ten years and allows individual orders to be drawn down periodically under that framework. It has monetary implications for non-delivery. They are called liquidated damages as opposed to penalties. The Cathaoirleach will know that you are not supposed to use penalties in a commercial contract. There are liquidated damages of certain levels involved. Irish Rail is currently liaising, if that is the right word, with the manufacturer in regard to the application of the contract and those damages.
Comment on this
Can we get a further note on that because it has had a knock-on impact? These were initially supposed to come into service in 2025. We were then told 2026 and we are now saying it is being pushed into 2027. There have been issues with the carriages that have been delivered. Were issues identified during the safety testing process?
Comment on this
There are always issues with new fleet, be it bus or rail. There will always be issues to be sorted out during the testing phase.
Comment on this
When we had the Department of Transport in previously, its officials said there were some additional concerns and that the process of testing was taking longer than anticipated and, until that process was concluded, the next batch of orders for additional carriages would not go through.
Comment on this
The technical issues referenced in the previous hearing that discussed this issue are the type that I have just referred to. Those technical issues are being addressed and we have received various assurances from the tram manufacturer in regard to that. Based on the assurances we have received, a third fleet order to replace life-expired DART carriages went through just before Christmas.
Comment on this
Are the safety issues being addressed? Does the NTA have no concerns in relation to them?
Comment on this
No, it does not. They have been addressed. In fact, I think the manufacturer was quite proactive in some of the safety things it did. It still caused a delay, but the manufacturer did the right thing. Not all manufacturers might have done it and we went ahead with the third order as a consequence.
Comment on this
In relation to Go-Ahead Ireland, Deputy Murphy touched on this issue and Mr. Creegan is no stranger to it. I have a path beaten to his door regarding my concerns with Go-Ahead Ireland and the poor service I see being delivered in my constituency of Wicklow. Given the plethora of financial penalties that had been imposed on Go-Ahead Ireland over previous years, I was honestly surprised and shocked when I heard it had been awarded another contract, which was signed off in November. I will not go over all the points made by Deputy Murphy, but I agree with those metrics that relate to Go-Ahead Ireland's failures. Even though a new contract has been awarded, I was in touch with the NTA again this week about the poor delivery of services within Wicklow.
I want to discuss the awarding of that contract. Will Mr. Ryan talk me through the awarding of that contract to Go-Ahead?
Comment on this
That was a competitively tendered contract and Go-Ahead bid for it.
Comment on this
I do not know that I am going to tell the Cathaoirleach that. I do not think that we should tell him that.
Comment on this
I would prefer if Mr. Ryan did tell me. I am not looking for names. I am just looking to see-----
Comment on this
There were no other bidders. That is what I expected to hear and that is setting off serious alarm bells. No other bidders came in. A service provider that delivered a very poor service over the previous number of years, essentially got the contract through default because there were no other bidders. Am I right in saying that?
Comment on this
No, because the contract has a set of award criteria and there is a minimum score a bidder must achieve under each of the quality criteria, as well as the price element. A bidder must meet those quality criteria in order to be able to be awarded the contract.
Comment on this
Given that there was only one bidder in for the contract, did the NTA look at any other alternatives in that process?
Comment on this
What does the Cathaoirleach mean by alternatives?
Comment on this
Did the NTA go back to the Department and raise concerns that there was only one bidder for that contract? Albeit I am not supporting the process, even Dublin Bus did not put in a bid for that contract. Were their concerns within the NTA?
Comment on this
We would have preferred more bidders, sure, but we cannot make Dublin Bus or any other operator bid for a contact.
Comment on this
Yes, having evaluated the tender submission and seeing that it met the quality criteria.
Comment on this
I heard the NTA's responses earlier in terms of Go-Ahead Ireland. Despite the litany of excuses that it has provided over the past five years and it continues to provide in terms of its inability to honour the contract it was awarded, is the authority happy with the service Go-Ahead Ireland is delivering now?
Comment on this
There are issues with all operators' performances from time to time and Go-Ahead Ireland is no different in that regard. Is it worse that other operators? We have been through that and the answer is "No, it is not". It has difficult enough operating environments in the outer areas of Dublin where there is not a bus priority, which certainly impacts on punctuality and reliability, to some extent. All operators have difficulties in different parts of their networks.
Comment on this
In terms of the transport budget for 2026, is the NTA happy with its allocation from the Government?
Comment on this
If the Cathaoirleach asked any State body if it is happy with the funding allocation it gets in the budget, it will probably tell him-----
Comment on this
Is the NTA satisfied that the delivery of new services that had been planned can and will be delivered via its allocation in budget 2026?
Comment on this
In terms of the services, there has been a big increase in the allocation to the NTA in budget 2026.
Comment on this
Is the NTA happy that it will be able to roll out new services and, for example, new routes that had been planned with the allocation that has been provided?
Comment on this
In regard to new routes and new services, that is something the NTA is in discussions with the Department of Transport on.
Comment on this
I asked that question because there was a concern among officials within the Department of Transport. A reply to an FOI request from a journalist from The Irish Times showed that the Department's management board met following the budget allocation and it stated that, while substantial, the allocation will not allow for new services to be delivered. The minutes of that particular meeting show the concerns expressed by senior officials within the Department of Transport. Will our witnesses from the Department give us more information on that?
Comment on this
Yes, no problem. We take a two-phased approach with regard to our upcoming budget for 2026.
Budget 2026 focuses on a significant increase that results in a 43% uplift on where we stood last year with our PSO allocation, as the Cathaoirleach noted himself. In that two-pronged approach, it is very important to look at maintaining and improving upon our existing network. With the high passenger numbers we have seen in recent times, when you provide public transport, who come to it. It is very important that we continue to invest in the capacity, punctuality and reliability of the network.
Comment on this
In terms of the concerns that were expressed at that meeting, maybe I can request the minutes from that particular meeting of the Department's management board. Could I ask for a copy of that to be furnished to the committee?
In terms of new routes that had been proposed, I will touch on that in my second contribution and allow other members in. What is the status of the new routes that had been envisaged to be rolled out in 2026 by the NTA? Will they now proceed as had been planned?
Comment on this
There are a few priorities for us in 2026. Priority number one is dealing with the capacity, punctuality and reliability on existing services. That is where our focus will be initially. As Mr. Creegan said, we are in discussions with the Department in relation to new services beyond that. Those discussions are ongoing.
Comment on this
I will allow other members back in. I am aware we are running a little behind schedule so if it is acceptable when allowing members back in for a second round, we will try to keep it to three minutes per member.
Comment on this
I thank the witnesses for staying on. Just to conclude on the project for the ramp and the steps, Mr. Creegan said if greater care was taken at the design stage, costs would have been reduced. What does that look like? Who was the designer? Was that somebody within Dún Laoghaire-Rathdown County Council or was that whoever the council had contracted?
Comment on this
I think Dún Laoghaire-Rathdown County Council contracted an engineering firm to do the design and a contracting firm to do the construction. My point was that the firm who did the engineering design, with the benefit of hindsight, probably could have picked up more things and optimised things further.
Comment on this
What did the engineering contractor that was contracted by Dún Laoghaire-Rathdown County Council not pick up on?
Comment on this
I am referring to the engineering designer.
Comment on this
We had issues with a number of things. One I mentioned earlier was underground utilities. Some of them were uncharted. That is usually hard to find out about but you can do an extensive site investigation and pick up more of them.
Comment on this
It had done some level of it. My point is that with hindsight - hindsight is brilliant - we could have done more. Some of the designer's quantification of what needed to be built could have been better than it was. There were a few technical things it just did not get fully right.
Comment on this
Does Mr. Creegan think the firm would share his assessment of its misgivings? Would it agree with what he is saying?
Comment on this
I think Dún Laoghaire-Rathdown County Council would agree with what I am saying. I have not spoken directly to the engineering firm so I cannot tell the Deputy what its viewpoint is.
Comment on this
To finish on what is hopefully a more positive note, I have raised with the NTA a number of times the Poolbeg Luas extension. I know I have been informed the feasibility study has been completed by TFI and is under consideration by the NTA. As Mr. Creegan knows, there is a real cost opportunity with synergy because the Dublin Port planning application involves the construction of a new bridge adjacent to the toll link bridge.
I just looked it up and in terms of where the 3FM planning application is at, a request for further information was responded to in October 2025. It seems we are at least a few months away from An Coimisiún Pleanála's decision. Let us assume it approves the 3FM Dublin Port expansion plan, which will involve the construction of a bridge. It is now feasible that the Poolbeg Luas extension plan could be advanced by the NTA so it could run concurrently with the construction of this bridge that would facilitate a Luas line going across that bridge?
Comment on this
I do not want to fully pre-empt our review of the documents we got in but that scenario of proceeding to extend the Luas is more compelling following the work that was done than it might have been previously. The provision of the new bridge the Deputy referred to, which Dublin Port is developing, has in its structural design provided to take the Luas track alongside it. That opens up new possibilities. If the Deputy gives us a couple more months, I cannot conclusively say at this stage where we will end up but we are much more favourably disposed, based on the evidence we now have, towards extending the Luas into the Poolbeg area using that bridge.
Comment on this
That is a very positive development and I am delighted to hear Mr. Creegan say that. I look forward to working with the NTA to advance this project for the community. I thank him.
Comment on this
I thank the witnesses for their time. I received a response that outlines the IT projects in the NTA between 2020 and 2025. I am really curious because nearly to a line, every project has come in on budget or significantly under budget. Without trying to be facetious - maybe I am becoming desensitised to IT projects in here - what is the key to getting projects delivered? All joking aside, some budget lines were €15 million and projects only cost €5 million. How is that? Is there a trend where the NTA is looking for too much money and it then the cost comes down? What is the overall approach to IT within the organisation?
Comment on this
There is a very strong project management office discipline in the organisation. Discipline is applied to the early work that goes into the cost-benefit analysis, the business case and the budgeting but there are also very structured fora for how the project is managed on an ongoing basis. A lot of those fora or steering groups involve the staff of the authority. They also involve the IT vendor as well. Over the years, it has been fine-tuned. It is not perfect in every single case but with the number of projects we have, there is a certain synergy across the organisation. Effectively, there are good project management skills and good budget management as well.
Comment on this
It is genuinely striking. It is something that is worth looking at for all members. We have seen so many examples of the opposite, in tabular form, in terms of how projects are budgeted for something and end up costing two, three or four times more. What we are seeing here is projects are consistently coming in at two or three times less than the cost we have budgeted for. That is really interesting.
I am very caught for time and I will not run over but I received a response to a parliamentary question from Irish Rail from September with regard to onboard catering for their rail services around the country. Essentially, it says the budget from the NTA to provide onboard catering is not sufficient to ensure a nationwide rollout. Has Irish Rail sought adequate funding for a comprehensive onboard catering service for all its rail services? What is the deficit? How much is outstanding that would cover the costs to make sure all rail services had catering available to them again?
Comment on this
In fairness, Irish Rail has sought a budget for this. Irish Rail tried to tender for the provision of these services a couple of years ago. A significant amount of money is required to provide catering services on all of the trains and all of the network. From memory, it is in the region of €2 million that would be required. The funding simply was not available to provide that. The information the Deputy has is correct. Irish Rail had sought money but that level of funding to provide the catering service just is not available.
Comment on this
Has the NTA sought that from the Department? Is the Department willing to look at this, given we are in 2026? Surely, it would be reasonable to expect that all rail services at this point could have a catering option available to them.
Comment on this
We acknowledge there is significant public interest in this space. It is key to the experience on public transport. However, as Mr. Creegan has alluded to, the costs have been significantly higher in the post-Covid period. We are looking at all avenues as to how we can fund that. In the balancing between providing our PSO allocation for the provision of services in quite a constrained scenario, the priority will go towards providing it for the services. However, we continue to explore every avenue we can and we are talking to the NTA and Irish Rail in that regard.
Comment on this
I have a few follow-up questions. I welcome the ordering of 100 new carriages over Christmas to replace the original DART fleet but they will not be deployed until at least 2028. Is Irish Rail confident the current fleet can be safely maintained until then? At what cost?
Comment on this
Irish Rail absolutely has the ability to maintain the fleet operational until the new fleet replaces them. The maintenance costs increase, though. As fleets get older and more things break down, it costs more. I do not have an exact number. I am not sure it is easy to abstract.
Comment on this
Does the Department have an estimate of the likely cost?
Comment on this
We do not have a definitive figure right now. We can follow up with the NTA if the Deputy wishes.
Comment on this
I would appreciate it. It is important to get an understanding of if we had ordered the carriages earlier whether we are costing ourselves money in the long run because we are not ordering carriages. As I raised previously with the Department and the NTA, I am really concerned about the small number of carriages and buses that have been ordered since both framework agreements were agreed.
I had raised in relation to the northern commuter line battery electric carriages and the delay until 2027. Is there anything that can be done in the meantime? Can we borrow, lease, beg – anything to try to improve the services? There is a huge population increase on the northern commuter line in towns like Balbriggan, Skerries, Rush and Lusk. Is there anything that can be done or will we get nothing until 2027?
Comment on this
In terms of train fleet, we have a unique gauge in Ireland, which makes getting trains at short notice really difficult. Realistically, no additional train fleet can be brought into service in Ireland this year. The new fleet is intended to go into service early next year. I do not see any way of bringing in additional fleet given our unique gauge and everything else.
Comment on this
We cannot borrow anything from Northern Ireland?
Comment on this
That has been asked and they do not have the fleet.
Comment on this
Communication is absolutely key. TFI has five different apps. The TFI app was down two days ago and there was no real time information. Whenever there are delays, they are not updated on the TFI app or at stations. There are huge issues with that. What can be done to try to communicate real time information? The current system just is not working. In train stations like Connolly, the screens regularly do not work and are not updated where there are serious delays to services.
Comment on this
I asked a few questions on this this week with the app down - I think it was down for about two or so hours – and about how we communicate disruptions information when things go wrong. There are areas of improvement we can do by working with the team. We are looking at how we can do some improvements to the current app and in the longer term looking at how we can consolidate-----
Comment on this
I would love if it was consolidated.
Comment on this
-----some of these things so that we can get better information out to customers. If there is anything I have learned, making sure customers have the right information to avoid disruption in the first place or communicate to them alternatives when something goes wrong on their usual commute is important.
Comment on this
The operators could use platforms other than Twitter, or X; it is the only reason I have that app. It is the only way to get real time information from Irish Rail when there are serious delays to the service.
Comment on this
That question was raised with me earlier this week.
Comment on this
Did the amount spent on PSOs increase hugely in 2024?
Comment on this
The PSO has seen a combination of unique phenomena post Covid in particular with a mix of extremely high levels of indexation, particularly on the various components that factor into it, for example, fuel, wage growth, and so on, which are essential to delivery of the programme. The other core element is the gap between income and expenditure, which has started widening significantly in the past number of years.
Comment on this
For the programme overall given we have lower than average fares across the board and a number of targeted fare initiatives.
Comment on this
Is that to cover a gap or are they new contracts? Is that a gap in costs for the operator because there are increased costs for the operators? Is that covered or are new schemes being put on?
Comment on this
The gap is between income in and expenditure out. The PSO formula is Exchequer allocation plus fare revenue; that equals the PSO programme. The gap between those two elements has increasingly widened. Of course, we have a budgetary allocation we receive as part of the annual Estimates process-----
Comment on this
We have to cover the gap. That is why this year in budget 2026 we are looking to restabilise that base. It is a key commitment under the programme for Government to look at a financial model for the PSO that is sustainable. We are also looking at reforming the programme.
Comment on this
Is there a risk there is a big black hole that is just getting bigger?
Comment on this
We have made significant efforts in the past two years, as the Deputy will see from reports, covering that but I will be frank. Last year, we needed an additional €192 million to deliver on the services we are required to under obligations and commitments to provide our citizens with a good service. That is why we are looking at reviewing that process as to how to finance the programme and avoid that happening now and into the future.
Comment on this
Rail fares were increased in some areas across the wider commuter area – Wicklow, Kilcock, Sallins and those sort of areas. The fares were decreased in some areas. What was the logic behind increasing fares? What modelling was done? What was the financial gain and benefit? What has been seen since?
Comment on this
We created a new fare structure in the greater Dublin area outside the 90-minute zone where the TFI 90 Leap card applies. The rationale was to create a more equitable fare system based on distance travelled. There was quite a variety or fares depending on whether you were on one bus or another and where you were in the greater Dublin area.
Comment on this
How much money was gained from increasing fares?
Comment on this
The scheme was designed to be revenue neutral. We did not plan to gain or lose revenue. Some people saw fare increases and some saw decreases.
Comment on this
Somebody lost and somebody gained. Mr. Ryan said it was cost neutral. What was the increase in revenue with the increase in fares etc.?
Comment on this
Mr. Ryan said it was revenue neutral overall. I want to know how much extra revenue was gained from the increased fares. That was offset by decreased fares.
Comment on this
I do not have that detail. That would be a very difficult question to answer.
Comment on this
I have no problem with that. Will Mr. Ryan come back with that?
Comment on this
I do not know if I could. I will inquire. It is a very difficult question to answer, thinking about it on the face of it. I will come back to the Deputy if we can.
Comment on this
There has been a significant increase in office accommodation. I am curious as to why. I know there is increased staff numbers. There are 46 extra people but the office accommodation went from €3 million to €5 million to €8 million in three years. Is that correct?
Comment on this
We had to source a new premises. The previous main HQ building we had was an OPW building and its lease was expiring so we went out to procurement. We moved into the new building from quarter 3 to quarter 4 of 2024. For a period, we inhabited the old office spaces and were also renting the new office space. There was an overlap in costs between the two buildings during that period.
Comment on this
It was approximately six months. Another item to mention is that during the negotiation phase with the new landlord, we agreed a one year rent-free period. The rent for the first year was free.
Comment on this
Yes we did. However, if the Deputy looks at the number he quoted from the financial statements, due to the accounting convention currently in place that one-year saving is spread out over the whole period.
Comment on this
It is spread out, yes. I am an accountant as well.
Comment on this
Very good. In cash terms, therefore, the cost is much lower in 2024, effectively, and we had that overlap as well.
Comment on this
But it is still significant. €3 million was the original baseline. When was it, 2022? Obviously it is not highlighted, but €3 million to €8 million is a huge jump if that is the case and if they are right-sized, if Mr. L'Estrange knows what I mean.
Comment on this
Yes and maybe a good comparator is 2023. That was a normal year in terms of the rental cost we had. The rental cost we had in 2023, when we had five different locations, was €4.4 million for rent with a service charge of €300,000, so all told it was over €4 million. If we look at the steady-state rent cost of our current single office building, we will see rent each year of €4.7 million including VAT and a service charge of €365,000 for a total bill of €5 million. We are looking at a steady-state rental charge of €5 million versus the €4.6 million that we incurred in 2023. We moved to a very sustainable building which is BER A-rated that generates lots of savings for us. We do not have to hire meeting rooms in hotels and so on as we can have all those things in-house, including public consultations on many of the large transport projects. The overall cost per square foot of the building we acquired was €48.50, which was the lowest price out of all the bids we got and represented very good value at the time in Dublin and a big reduction on the area we previously inhabited up at Harcourt Lane. Overall, it is good value for money.
Comment on this
Okay, but Mr. L'Estrange can see why I asked the question.
Comment on this
I have a few concluding questions. Again, thanks very much to the officials for staying on. On fares and structures, are there any reviews of fares ongoing across the board?
Comment on this
We are looking at structures outside Dublin now. We looked at the structure in the greater Dublin area and introduced the fare changes there, as the Cathaoirleach knows, last year. We are looking at Cork next and we hope to be getting those in place in Cork city in the first half of this year. There is not an exact date on that. It depends a little on the new ticket machines we are bringing on board Cork buses. In the background we are looking at Limerick and Galway as well to get them into the same sort of distance-based fare structure, or flat fare in the city itself. We are also looking outside the cities at getting a revised fare structure that is, again, distance-based. It is all with a view to having a revenue-neutral but fairer fare scheme for people.
Comment on this
I appreciate that. On the distance-related fare structure, the NTA has finished the piece of work in Dublin. Even looking at the baseline figures there, is the cost to use public transport being looked at in terms of increasing the overall charges customers pay?
Comment on this
Just to note, there was the cost-of-living fare reduction in 2022. It was a 20% reduction in fares that I think was originally intended to be reversed at the end of that year, but it is still in place. There have also been significant decreases as the young adult and student card was rolled out and the age validity was extended, with under-nines now going free and over-70s now allowed to take a non-fare-paying passenger on board to accompany them.
Comment on this
Fare revenues have suffered as a result. It is just something to note in the round and obviously something we are speaking to the Department about.
Comment on this
As Ms Brady said in terms of the OECD report around PSO and putting it on a more sustainable funding basis, it is one of the aspects, no doubt, that will be looked at in that report.
Comment on this
Okay, so on recommendations coming from the NTA at this stage, would the authority be proposing that there be a fare increase?
Comment on this
We are not making any recommendations at this stage.
Comment on this
He cannot rule it out, okay. Will any fare increase ultimately be a matter for the Minister to approve or what is the protocol?
Comment on this
The authority needs to consult the Minister but it does not need ministerial approval.
Comment on this
I might give a little more clarity on that. As I said to Deputy Neville, we are looking at a review of the public transport financing model as a whole and obviously a core component of that is the PSO programme. We will be looking to bring in the OECD, which as members are aware is a multilateral organisation that has a number of best practice approaches in that regard. As fare renewal is a key part of the PSO equation, we would be remiss not to look at it as one of the core pillars of how a number of other jurisdictions internationally fund public transport. It will be a wider approach looking at how we can utilise all avenues of public transport financing.
Comment on this
Okay. I want to move on to two other areas quickly. Park and ride facilities were touched on there in relation to Louth. Obviously another key part of that is at the southern end of the N11-M11. There are three proposed park and rides along the N11. One is constructed and just waiting to be activated, which is positive. I got an update on that and hope to see it open as soon as possible. Could I get an update on the second park and ride at Ashford-Rathnew? I take it that it is the NTA that funds all these projects.
Comment on this
Yes. We are leading on all of those strategic park and ride sites. Fassaroe, which is the one the Cathaoirleach mentioned first, is virtually complete. With the other two I think we are better off sending a note afterwards because I am slightly unsure of the position on both of them. I think we are close to a planning permission application for one of them and the other one is a little bit behind, but perhaps I will send a note.
Comment on this
I want to tease it out briefly if that is okay. Approval for the Ashford-Rathnew site, with 210 parking spaces, was given by Wicklow County Council in March of last year, I think. The expectation, based on what was said at that meeting, was that construction would commence and the facility would be delivered by quarter 4 of this year. That was stated at the meeting in March last year. I got a note from the NTA to say that this is not now happening, that there are issues with funding, that it is questionable that there will be any funding to see that project commence at all in 2026 and that it will be dependent on funding in 2027. That is of serious concern to me because this has been promised, is long anticipated and is badly needed. That is the most current position on it and Mr. Creegan may correct me if I am wrong.
Comment on this
I am not going to correct that because I think the Cathaoirleach is right, but we will still send him a note on the funding because I am not exactly sure how much we have allocated to it. We are not able to be-----
Comment on this
What I am trying to get to is that a commitment was given at a full council meeting.
Comment on this
Was funding in place at that stage? Otherwise, commitments should not and could not have been given that this was due to commence in 2026.
Comment on this
I was not at that meeting so I do not know what way it was phrased. Our funding is largely on an annual basis, so we needed to wait until budget 2026 to know what our funding would be for 2026. We know that now. I will get it checked out. We will send the committee a note confirming what the position is. I do not know the exact way that commitment was phrased at that meeting.
Comment on this
Okay. I want to touch on another issue. Local Link services have been mentioned by a number of Members. Local Link is a brilliant service that delivers public transport right into the heart of rural communities and, similarly, in my own constituency of Wicklow. A number of years ago, in 2024, there was a welcome announcement that a new route, the 199, would be delivered between Glendalough and Bray, and would serve places like Roundwood and Laragh. It has proven very difficult to get information on the new service. I am quite concerned about the response I got from the NTA to a parliamentary question I tabled on the matter. It stated that the project is caught up in the PSO discussions. I have many concerns in relation to this. The new route was to be rolled out last year. A contract was entered into with a contractor who hired additional staff to ensure the route was rolled out. A public announcement was made that the service was due to come into effect on 22 September 2025. Obviously the contractor had geared up and was ready to go and the public eagerly awaited the roll-out of this service. The latest response to one of my parliamentary questions is that the new service is caught up in the PSO discussions. Was funding in place for this route? How could a contract be entered into with a service provider without a clear line of funding being in place?
Comment on this
I will come back with details on that because I am not entirely sure. I suspect that a contract was not signed but let me double-check.
Comment on this
A public announcement was made that the service was due to come into operation on 22 September 2025. That never happened. Now I have been told that the service is caught up in discussions. Previous responses by the NTA gave a delivery timeline and stated that the project was at an advanced stage of negotiations in terms of appointing a contractor to deliver the service, but it never happened.
Comment on this
Whatever information we gave out was the correct information at the point in time. I am sure of that. Let us put a note together on it because neither Mr. Ryan nor I can confirm whether that contract was signed and what form the announcement took. It may be that we responded to a parliamentary question by saying we expected that this route would come into place on 22 September. Let us check it out and come back with a more-----
Comment on this
Okay. I do not know whether Mr. Creegan has the information now but the public want to know and need to know when the service will be rolled out as it has been talked about since 2024.
Comment on this
I think this goes back to the discussions we are having with the Department in regard to new services. We are not in a position to confirm any date here.
Comment on this
Okay. Previously, senior officials in the Department had serious concerns that the level of funding would not be sufficient to roll out new services. Is this new service caught up in those concerns expressed by senior officials within the Department?
Comment on this
I think it is part of the discussions around these services. As we have said already a few times, they are ongoing in this Department.
Comment on this
Perhaps the NTA could provide a note on whether other Local Link routes are caught up in a similar situation to the proposed 199 route in County Wicklow. Can Mr. Creegan give categorical assurances that the proposed route will be operational in quarter 1 of this year?
Comment on this
We are not in a position to do that here and now.
Comment on this
It is little comfort that the witnesses are not in a position to say that. We need a note on the matter. We need clarity about the concerns of senior officials about the funding being delivered in budget 2026. We need to see the minutes of those meetings. Those concerns, as revealed on foot of a freedom of information request, said that funding issues would have an impact on the delivery of new services in 2026. I fear that the park and ride site in Wicklow and the roll-out of the Local Link 199 route are caught up in that. Both examples concern my constituency but the issue is broader and spans the State. Therefore, I request a full note from the Department and the NTA on the discussions. We need the details of what routes are caught up in this. We need to know what additional new services are caught up, or potentially caught up, in this process.
Comment on this
Thanks for that. We will now conclude our engagement for today. I thank the witnesses for staying longer than expected and I apologise for that. I thank the chief executive officer and her officials from the NTA for attending. I thank the officials from the Department of Transport, and the Comptroller and Auditor General and his officials for their attendance again here today. Is it agreed that the clerk will seek any follow-up information and carry out any agreed actions arising from the meeting? Agreed.
The committee's next meeting is on Thursday, 22 January, when we will engage with officials from St. James's Hospital.