The Minister forecast service early next year, while Fahey challenged the delay and an unfulfilled commitment. The Minister attributed difficulties to the Ballinamult building, expected in 1979 but handed over in January 1981, and said he had no further explanation for the late completion.

asked the Minister for Posts and Telegraphs when an automatic telephone service will be provided for the Ballinamult area, County Waterford.

Comment on this

: Early next year.

Comment on this

: Could the Minister give the reason why there was such a long delay?

Comment on this

: There was no undue delay. Like every other place, service will be provided as soon as possible.

Comment on this

: Surely the Minister is not serious when he gives that type of reply. There has been a long delay in this case and a commitment was given a long time ago——

Comment on this
Thomas J. Fitzpatrick An Ceann Comhairle Fine Gael

: A question please, Deputy.

Comment on this

: ——which has not been honoured. Why do we have to wait until next year for a service which was ready last year? What difficulties arose in the provision of this service?

Comment on this

: I am giving the Deputy a commitment that the service will be provided next year.

Comment on this

: Is the Minister saying no difficulties were encountered as regards the provision of this service?

Comment on this

: Considerable difficulties have been experienced in providing the Ballinamult building. Completion was expected in 1979 but the contractors did not hand over the building until January 1981.

Comment on this

: First the Minister said there was no delay involved in the provision of this service but he has now admitted there was. Perhaps now he will answer my supplementary. What caused the delay and what length of time was involved?

Comment on this

: Completion of the building was expected in 1979 but it was not completed until January 1981.

Comment on this

: Why was the building not finished by the given date? What happened?

Comment on this

: These were golden years when Deputy Fahey's party were in power.

Comment on this

: I have no explanation.

Comment on this

: These were the good times and we are supposed to be on our knees praying to get back to them.