Written answer
Defence Forces
167. Deputy Catherine Murphy asked the Tánaiste and Minister for Defence the capital works carried going at Defence Forces headquarters; when each of those capital works projects will be completed; and the capital works projects at Defence Forces headquarters that will commence in 2025, in tabular form. [44848/24]
Comment on this
The Defence Forces headquarters are jointly situated in McKee and the Curragh barracks; whilst also having HQ offices in Baldonnel Aerodrome, Haulbowline and Newbridge (DFHQ and Department of Defence). Please find a list of capital works projects either ongoing in 2024 or due to commence in 2025.
Existing Projects | Location | Start | Completed
Refurbishment of ‘F’ Block | McKee Bks | Q2 2023 | Q4 2024
Refurbishment of Locker Block | McKee Bks | Q2 2024 | Q1 2025
Upgrade of heating system | Newbridge | Q2 2024 | Q4 2024
2025 Projects | Location | Start | Completed
Refurbishment of CIS Building | McKee Bks | Q2 2025 | Q1 2026
New ARW HQ | Curragh Camp | Q1 2025 | Q2 2026
Installation of EV charging Points | Newbridge | Q2 2025 | Q3 2025
Office refurbishment (multiple locations) | Newbridge | Q4 2024 | Q1 2025
Upgrade of CCTV system | Newbridge | Q2 2025 | Q3 2025
Security upgrade to main reception | Newbridge | Q2 2025 | Q3 2025