407. Deputy Gary Gannon asked the Minister for Education and Youth if she will provide an update on the building works at a school (details supplied); whether a new contractor has now been appointed to recommence works on the project; and if so, when works are expected to recommence on site; and if she will make a statement on the matter. [51896/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

The new build for the school referred to by the Deputy is a large-scale capital project for the construction of a 16-classroom primary school in Dublin 1.

The building project to complete the new build for Gaelscoil Choláiste Mhuire, Dominick Street, is at stage 3 of the architectural planning process - tender action and award.

The Department can confirm that following a confidential conciliation process concerning all matters in dispute between the Department and the original contractor, the conciliator has now issued a formal recommendation for the resolution of those disputes, and that recommendation has now been accepted by both parties.

Following the conclusion of the conciliation process, my Department has instructed the design team to ready a tender for the completion contract for the school in Dominick Street.

This process is expected to take four to six weeks to publish the tender, with a view to having a contractor on-site in early quarter 4 of 2026.

It remains the Department’s priority to deliver a new school building for Gaelscoil Choláiste Mhuire as quickly as possible. Departmental officials will continue to work closely with the school authority.