Rail Network

137. Deputy Rory Hearne asked the Minister for Transport if he still expects construction on the Luas Finglas to begin in 2028 as per a news report (details supplied). [67022/26]

Comment on this

138. Deputy Rory Hearne asked the Minister for Transport further to a report (details supplied), to outline the details of any spending package that has been allocated for the Luas Finglas project and to outline the level of funding, if any, that has been drawn down or will be drawn down from the climate and nature fund for the delivery of the project. [67021/26]

Comment on this

139. Deputy Rory Hearne asked the Minister for Transport to outline the current funding being made available by his Department for the delivery of the Luas Finglas project; and to outline any planned or anticipated additional funding for the project. [67019/26]

Comment on this

143. Deputy Rory Hearne asked the Minister for Transport to provide an update on the current estimated timeframe for the delivery of Luas Finglas. [67012/26]

Comment on this
Darragh O'Brien Minister for Transport Fianna Fáil

I propose to take Questions Nos. 137, 138, 139 and 143 together.

As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of Public transport infrastructure including light rail.

Luas Finglas is an exciting project that has the potential to transform Finglas and the wider area.

Government's consent for approval for the project to proceed at Approval Gate 1 of the Infrastructure Guidelines was obtained on 22 October 2024. An Coimisiún Pleanála published its decision to grant the Luas Finglas Railway Order in October 2025. I warmly welcome the subsequent withdrawal of a legal challenges, as it means that we now have full planning permission in place to move forward with the Luas Finglas extension.

Luas Finglas is one of the four light rail proposals identified for development and delivery within the lifetime of the NTA Transport Strategy for the Greater Dublin Area 2022-2042. The project is identified in the Sectoral Investment Plan for Transport as part of the National Development Plan Review 2025. Specifically, under the Sectoral Investment Plan, the main construction works will commence by 2029, and some enabling works may commence beforehand.

I understand that Transport Infrastructure Ireland (TII) is currently preparing the Approval Gate 2 documentation, which is expected to be submitted to my Department and the NTA in Quarter 4 2026.

Noting the NTA's responsibility the Luas Finglas project, I have referred the Deputy's questions to the NTA for a direct reply. Please contact my private office within 10 days.