Written answer
Housing Provision
The Minister provided tabulated information on accelerated CALF funding, projects and AHBs for 2015–2026, explaining how the facility supports social housing delivery. Fifteen projects approved for accelerated CALF have yet to commence on site; project delivery may span multiple years.
1034. Deputy Rory Hearne asked the Minister for Housing, Local Government and Heritage the amount of accelerated CALF approved in 2026; the number of individual projects approved; and the number of AHBs these projects relate to, in tabular form. [75561/26]
Comment on this
1038. Deputy Rory Hearne asked the Minister for Housing, Local Government and Heritage the amount of accelerated CALF repaid for projects that received funds but subsequently did not commence for the years 2015 to 2025, in tabular form. [75560/26]
Comment on this
1039. Deputy Rory Hearne asked the Minister for Housing, Local Government and Heritage the number of projects that received accelerated CALF; the number of projects commenced, the number of projects yet to commence; and the number of projects completed for the years 2015 to 2025, in tabular form. [75559/26]
Comment on this
1040. Deputy Rory Hearne asked the Minister for Housing, Local Government and Heritage the number of AHBs that received accelerated CALF for the years 2015 to 2025, in tabular form. [75558/26]
Comment on this
1041. Deputy Rory Hearne asked the Minister for Housing, Local Government and Heritage the amount of accelerated CALF provided to AHBs; and the number of individual projects that received accelerated CALF for the years 2015 to 2025, inclusive. [75555/26]
Comment on this
I propose to take Questions Nos. 1034 and 1038 to 1041, inclusive, together.
I propose to take questions (75555/26, 75558/26, 75559/26, 75560/26 and 75561/26) together and I have set out the information requested in the table below.
My Department operates a number of funding programmes that assist local authorities to work in partnership with Approved Housing Bodies (AHBs) to construct and purchase new homes and make them available for social housing. The main funding programme that AHBs progress Social Housing projects through is the Capital Advance Leasing Facility (CALF).
CALF funding is capital support provided to Approved Housing Bodies (AHBs) by local authorities which fund the construction or purchase of new build social housing units. This loan facility can support between 25% and 30% of the eligible capital cost of the housing project, with the remaining finance sourced by the AHBs from private lenders (usually the Housing Finance Agency (HFA).
Accelerated CALF is where an AHB can request to drawdown up to 95% of the CALF amount approved, based on vouched expenditure, for a specific project during the delivery phase, with 5% retained until the signing of the P&A Agreement. Accelerated CALF must be outlined in the initial application and provided for in the CALF approval letter. Minimum draw-down amounts for Accelerated CALF payments can be set down in the loan agreement. Accelerated CALF is used by the AHB sector in the larger construction projects and in relation to acquiring projects through site purchase and stage payment arrangements.
CALF supported projects are at various stages of development and monitored closely by AHBs, Local Authorities and the Department. Currently, there are 15 projects yet to commence on site that have been approved for Accelerated CALF.
It should be noted that:
1. Due to the multi-year nature of the CALF funding model, delivery of new housing does not always arise in the same year as expenditure and projects delivered under phased programmes may cross a number of payment periods.
2. The information in Table A is the most up-to-date financial information available.
3. Projects commenced in the years listed above were not necessarily approved in the same year.
Table A