Saincheisteanna Tráthúla - Topical Issue Debate ›
Schools Refurbishment
St. Brigid’s National School needs urgent refurbishment after decades of delay, with unsafe, deteriorating buildings and uncertainty over its planned 17-classroom and three-SEN-classroom project. The Department says the project’s stage 2a report is under review and is progressing, but gave no timeline, promising only to advance it at the earliest opportunity.
St. Brigid's national school sits on a small site in the community of Foxrock, where approximately 400 children go to school every day. The original schoolhouse is over 112 years old. It is a protected structure and is in need of major restorative works. As it stands, it is not fit for purpose. There are also two dilapidated prefabs where further classrooms are located. As many people who went to national schools will know, prefabs were installed as temporary measures. They have an expected lifespan of about ten years. One of the prefabs at St. Brigid's is now about 40 years old. The building is rotten. There are holes in classroom floors that staff have had to patch themselves so that students and staff do not fall through. There is mould in the principal's office and it is spreading uncontrollably over files stashed in what limited space there is. Mr. Flood has to work with the window open to protect his health, so of course his office is freezing. The skylight in the secretary's office is so old and bowed inwards that birds bathe in it after it rains. Most classrooms have buckets to catch the rainwater when it starts dripping through the ceiling.
In one prefab, 15 female teachers, hard-working professional adults, must share one toilet between them at break time but it barely flushes. All the toilets in these antiquated prefabs take about ten minutes to refill after a flush. Ms Ramirez showed my team the basins that staff and students have to use to ensure the toilet is properly flushed after them. The bathroom facilities are, to put it succinctly, grim. Add to this the indignity of having to use a toilet that is literally within the classroom, separated by thin partition walls. The toilets in the old building are cold and smelly. Students do not like using them, so they often hold it in all day. There are large cracks in the walls of the old building, the plaster is falling off and the wind is coming through. The staff room is never quiet or private because it is a throughway for students to get from one part of the school to the other. The roof on one prefab received an emergency patch job in 2023 because it was leaking. Money was spent on maintaining a crumbling building that was no longer fit for purpose. This is in Foxrock in 2026. It is one of the most affluent areas in this country. The school is losing pupils, and who would send their child there after visiting for an open day?
Conversations with the Department of education regarding building upgrades have been ongoing since 1996 to coincide with the supposed retirement of the prefabs that turned ten years old that year. Thirty years later, nothing has been done. In 2018, St. Brigid's board of management received positive updates from the Department and was asked to fill out application forms for upgrades, and nothing happened. In 2023, the Department confirmed that the school's building project would go ahead under the accelerated delivery of architectural planning and tendering, ADAPT, programme, with a construction date planned for spring 2026 to be completed by autumn 2027. Three years after the school applied to the ADAPT programme and with almost €500,000 spent by the school on planning and architectural plans in preparation for this long overdue renovation, the project stalled without communication from the Department. There was radio silence. The school then received unofficial word that it will be 2031 before the renovations could start.
I point out that there was a delay in the progress of the project because the Department wanted the plans to be changed. It wanted a third special educational needs class, so the architects amended the plans and resubmitted them.
Approval for the new design is supposed to take one month. Nine months after submitting the new plans that the Department strongly recommended, the school has heard nothing. Nobody will answer their questions. Will the Minister of State ensure the plans submitted to the Department approximately nine months ago are approved? If there are any outstanding issues with the plans, will he communicate clearly with the school and project management team so the project can move to the next stage? Will he commit to an estimated timeline for this? Will he confirm what the plan is for decanting St. Brigid's while construction is under way? I have plenty more detail to provide to him.
Comment on this
I thank Deputy Gibney for raising this important matter. I am taking it on behalf of the Minister for education, Deputy Naughton. I recognise the importance of the project, not just for the pupils but for students, staff and the wider school community. The proposed project represents significant investment in education infrastructure and will deliver a 17-classroom primary school, together with three special educational needs classrooms. That will ensure the school can continue to meet the needs of current and future pupils.
The project is at stage 2a, developed design, a critical phase during which the design is further developed, costed and refined, and preparation is made of the statutory approvals. The stage 2a report was submitted to the Department in February of this year and is undergoing the necessary due diligence review. On completion of the process, engagement will take place with the project manager and the school regarding the next stakeholder meeting. While I appreciate school communities naturally want projects to move on as quickly as possible, it is important all major school building projects progress through each stage in accordance with the Government's infrastructure guidelines and capital works management framework. Government remains committed to investing significantly in school infrastructure nationwide. A total capital allocation of over €7.55 billion has been confirmed by the Department of education under the national development plan for the period out to 2030. Emphasis will be placed on the provision of accommodation for children with special educational needs and ensuring school place requirements can continue to be met across the country.
Across the school building programme, approximately 1,000 projects of varying scale will be on-site during 2026. This represents one of the most significant periods of investment ever undertaken in the education sphere. Since 2020, over €2.1 billion in capital funding has been invested in Dublin schools, with hundreds of projects delivered through new school building programmes, expansions, modular accommodation and other improvement works. The Government remains committed to delivering modern education facilities, including at St. Brigid's, expanding SEN provision and ensuring investment is targeted where it can have the greatest impact on students, families and school communities.
Comment on this
I want to give a shout-out to the teaching staff and entire school community. I will never cease to be amazed by the ingenuity and resourcefulness of teachers in the Irish public education system. Unfortunately, they have to show those qualities when dealing with stagnant funding and increasing complexities in childhood education. I share my most heartfelt respect for the dedicated staff of St. Brigid's. They have squeezed sensory areas into every corner they can find to provide calming areas for children with complex sensory needs.
Despite all the grim circumstances I have described in St. Brigid's school and the grim predictions, the community of staff, students and families is warm, united and dedicated. They adore their school community. It is a multigenerational community. Parents who went there now send their children there. The principal's young son is a student. Ms Ramirez was a pupil there and is now a senior teacher. She teaches in the same prefab she attended as a child. The senior staff and board of management decided to keep the project secret so as not to get everyone's hopes up. The lack of clarity from the Department has prevented the school moving forward with other big projects and management decisions but they have now decided to share this with me and their other TDs because they cannot wait any longer. They have informed the entire school. The children and staff cheered with delight upon hearing it. The parents are chatting excitedly at the gates.
After three decades of promised renovations for these incredibly difficult circumstances in which people are trying to teach and learn and a predicted five-year delay until 2031 before it can start, will this Government and the Minister of State please commit to doing this immediately?
Comment on this
I again thank the Deputy for raising this important matter. I completely understand the frustration from the parents, staff and wider school community, who want to see visible progress and understandably want certainty regarding the timeline. The important point is that this project is active and progressing. The stage 2a report on the proposed development was delivered in February of this year and it is an enormous project, with 17 classrooms and three SEN classrooms, which is a substantial investment in the future of the St. Brigid's school. I do not want to mislead the House by giving dates that cannot yet be guaranteed. I know the Minister, Deputy Naughton, is working on future capital programmes. The Department is very much committed to progressing projects as quickly as possible and ensuring the appropriate oversight is in place where there is value for money and compliance with all the requirements. Schools are being delivered right across the country. There is record investment in the schools capital programme. The focus of the Minister and the Department will ensure St. Brigid's Boys' National School advances successfully to the next stage at the earliest possible opportunity so that this important investment can ultimately be delivered for the pupils, parents and wider school community.