Financial Statements 2025: Uisce Éireann
Uisce Éireann reported 2025 revenue of about €1.8 billion and capital investment of €1.43 billion, with profits reinvested in infrastructure; the Comptroller and Auditor General issued a clean audit opinion. The CRU’s €31 million reduction in future allowed revenue for missed leakage and non-domestic collection targets was accepted by the utility, which said it would deliver efficiencies to absorb the impact. Uisce Éireann outlined a €12.2 billion investment programme focused on network upgrades and housing capacity, while acknowledging ongoing service and communication challenges. Committee members also questioned executive pay and performance awards, the funding model, procurement transparency and the pace of local projects.
Contributions 646–865 of 1,084. This sitting's record is too long for one page, so it is split into 5 parts.
Just to be clear, when the witnesses are presenting the facts here, they have no skin in the game here when it comes to the data centre industry.
Comment on this
The witnesses are just telling us how much water data centres use.
Comment on this
Data centres are just another industrial or business user to us. There is no policy in the country about data centres. If somebody comes to us looking for a connection, we assess them based on their consumption.
Comment on this
The regulatory body for Uisce Éireann is the CRU. Is that correct?
Comment on this
When witnesses from the CRU were before the Committee on Artificial Intelligence, they relied on Uisce Éireann's figures in relation to water usage and presented them to the committee.
I want to go back to the salary issue. Mr. Gleeson said, "We do not get increments, but we do get ... pay increases." By that does he mean that there are no salary scales within Irish Water?
Comment on this
Mr. McCarthy might explain the difference between public sector increments and our-----
Comment on this
Increments normally mean there is a salary scale and people move up it.
Comment on this
Are there no salary scales or salary bands within Irish Water?
Comment on this
What point was Mr. Gleeson trying to make when he said, "We do not get increments, but we do get ... pay increases?"
Comment on this
The salary bands are based on promotions.
Comment on this
I might take this. In the public sector, you get increments and you get a wage increase every year, so you get two increases. In our case, we get a PRA, so that is the situation. Currently, there is a wage agreement. In our model----
Comment on this
I understand what increments are. Mr. McCarthy said Irish Water has salary bands as well. Do the workers move up salary bands?
Comment on this
No. You would have to get a promotion or find a new job to move up.
Comment on this
No. If you stay in the same role, you just get your annual pay increase based on the cost of living. You do not get increments.
Comment on this
Is it common for people to move up salary bands in the organisation?
Comment on this
No, you have to go through a recruitment process and be interviewed to move up the band.
Comment on this
It is not common for people to move out of their existing salary band. Is that correct?
Comment on this
Obviously, retention is important and we want people to stay in the organisation so we would welcome people moving, but it is not common.
Comment on this
Earlier, Mr. McCarthy made a virtue of the fact that employees get performance-related pay but said they must perform and that if they do not perform, they do not get the pay. That is a joke, is it not?
Comment on this
It is a joke because every single person, without exception, gets a bonus in Irish Water. Did Mr. Gleeson mention eight people who did not get it last year?
Comment on this
That is 18 out of how many employees?
Comment on this
I hope those 18 people are not watching this committee hearing now, because I would say they would be fairly upset knowing that every single other employee in the organisation got a pay increment. That is a joke. How can it not be considered anything other than a joke? I am not saying those people are not entitled to the moneys they got. However, in terms of performance-related pay benchmarked against the private sector, is it common that performance-related pay would be to that level?
Comment on this
Absolutely. We operate a normal distribution bell curve. Approximately 70% of people are in the centre. That is the normal distribution. In our case, in 2025, we had 74%. It operates on "exceeds - 20%" and we had 18%. "Behind" is 10% and we had 8%. On balance, we are curved very effectively and that is not a forced distribution.
Comment on this
I do not doubt that the totality of the salary is curved well and benchmarked against the private sector. I am just saying-----
Comment on this
No, I am saying that the performance is curved. We do not have a performance model whereby we want people to fail. We want them to achieve, because if they do, the organisation's overall objectives are achieved. That is the purpose of having an incentivised model, and it is paid rates-----
Comment on this
The challenge, though, in the public sector, as Mr. McCarthy knows, is that it is difficult for us on this side of the desk to understand why bonuses are being paid out to every single employee within Irish Water, and that is not a common approach in other public sector bodies.
Comment on this
Not in the public sector, but it is very common in all the semi-State bodies and we are a semi-State, commercial utility. All have PRA models or variable pay.
Comment on this
However, as the officials know, the others do not get the €1.2 billion dividend Uisce Éireann gets.
Comment on this
-----a government decision. I beg your pardon; that is a government decision.
Comment on this
It is not Uisce Éireann's fault-----
Comment on this
-----but it is up to us to question it. I accept that.
Comment on this
It is the government's decision but it is important to realise the regulator has a very important role. It is the economic regulator and it is responsible for the value for money at all levels. That sometimes gets missed.
Comment on this
Mr. McCarthy mentioned that pensions were a big issue in the context of whether the utility moves from increments or performance-related pay. Will he explain what he meant by that? Is the performance-related element of pay not accruable for the purpose of a pension?
Comment on this
Absolutely not and it is not consolidated either.
Comment on this
As in you will not get your increase on that, year on year.
Comment on this
Last year Ms O'Dwyer told us: "In 2024, our customers accepted 4,252 connection offers and they were ... associated with 41,169 housing units". What do those figures look like for 2025?
Comment on this
For 2025 pre-connection inquiries, we were able to issue positive response for 4,979 applications. They were associated with 182,689 units.
Comment on this
Hold on. Ms O'Dwyer said 41,000 housing units last year.
Comment on this
I am coming to that one. For connection offers, which is where someone applied for a connection, we issued offers for 41,903 units. Then in terms-----
Comment on this
So it has flatlined. The number of housing units the utility has built connections for is the exact same as last year.
Comment on this
That is 2024 to 2025. I can give the Deputy some of the latest figures we are seeing for 2026 if he wants them.
Comment on this
Last year, Mr. Laffey said Uisce Éireann was trying to get to a target of 50,000 but it seems despite huge investment from the State, it is at the exact same level.
Comment on this
Yes but we are dependent on people coming to us looking for those applications. That is not something we drive. The Deputy has to look at the rejection rate as well. Can Ms O'Dwyer give those figures?
Comment on this
Maybe I will give those figures for 2026. We are seeing activity trending up in 2026 versus 2025. Year to date in 2026 we have seen the pre-connection inquires we have issued increasing significantly and the same with the connection offers. We are trending ahead versus where we were this time last year. I am sorry; I was trying to locate them. Talking and trying to find information at the same time is never a good idea. We are seeing the offers trending up and the big-----
Comment on this
Does Ms O'Dwyer have a year-to-date figure, for example, for connection offers associated with housing units for 2026?
Comment on this
I do. For 2026 connection offers, up to the end of August we had issued offers associated with 31,000 housing units. For pre-connection inquires, positive responses out associated with 147,914 units, so-----
Comment on this
On the 31,000 figure from August, Ms O'Dwyer probably does not have those figures right in front of her but what did it look like in August 2025, for example?
Comment on this
If you just pro rata that on a monthly basis, that is trending up to outperform where we were this time last year.
Comment on this
If we did pro rata that, what does that look like at year end?
Comment on this
I am going to say just under 48,000, so it is trending up.
Comment on this
Then it will be close to the 50,000 figure by year end.
Comment on this
Yes. Activity is trending up. Another thing we would like to highlight is our turnaround time. We have increased the resources in our connections and developer services team that is supporting developers and our response rate has really increased. For pre-connection inquiries in 2025, we were responding to 78% within 16 weeks. We have increased that to 93%. With connection applications, our performance was 72% in 2025 and we have stepped that up to an 84% response rate within 16 weeks so far this year. We deployed resources to that area to support housing.
Mr. Gleeson asked me to touch on the refusals. Our refusals, which is where we cannot facilitate offers, are less than 1%. It is a really small figure. We endeavour to work with the development community so they can understand where we have capacity and we are working together effectively to enable housing.
Comment on this
I have a number of questions of my own. In 2025, how many EPA prosecutions were there against Uisce Éireann?
Comment on this
Mr. Laffey can probably come in. Has he those figures?
Comment on this
We accepted the prosecution in most cases.
Comment on this
It is disclosed in the accounts, actually.
Comment on this
They are in the accounts but I do not have it to hand. We will get it to the Chair before the end of these questions.
Comment on this
Come back to us. How did the number of prosecutions by the EPA compare with the 2024 figure?
Comment on this
You might come back to me. What about prosecutions by Inland Fisheries Ireland in 2025?
Comment on this
I think they are in the annual report as well.
Comment on this
There are seven of them and four of the - on a combined basis it is about 100.
Comment on this
Someone might enlighten me on the European Commission referring Ireland to the European Court of Justice in the context of the EU wastewater directive. What is the current status of that?
Comment on this
I might get Mr. Laffey to come in on that.
Comment on this
We have received notification from the court that it is minded to impose fines and we are working with our Department to present a final case back to it.
Comment on this
They would be substantial and backdated to about 2019.
Comment on this
I do not have the figures but we are talking about tens of millions of euro.
Comment on this
One bright spark is that Ringsend wastewater treatment plant has come into compliance.
Comment on this
I asked those questions because of the performance-related bonuses. Successful cases are being taken against Uisce Éireann by the EPA and Inland Fisheries Ireland. We have the CRU, an adjustment of €31 million and then also substantial financial penalties looming from the European Court of Justice. That goes back to 2019. Just to get my own thoughts right, the PRA bonuses are separate to the 3% cost-of-living adjustment or increase that was alluded to. I think reference was made to three-year agreement that had been negotiated.
Comment on this
What is agreed is 3% but if people do not perform, they will not get the full 3%.
Comment on this
Their line manager. Their manager would set their targets and at the end of the year assess whether they have met them or not.
Comment on this
We have two separate financial packages, essentially, that are both performance-related. One is the PRA and then this separate 3% increase. Do you find that unusual or is it the norm in your experience?
Comment on this
That is the norm in semi-States. It is the norm in the private sector and I suppose-----
Comment on this
Is it the norm? Can Mr. McCarthy refer to me to any other semi-State that has a PRA bonus?
Comment on this
I think there was a State body in the media over the weekend.
Comment on this
The ESB has, as well as GNI, Coillte, Bord na Móna and I could keep naming them.
Comment on this
Again, the line manager sets the individual targets and then the board approves the overall company targets. It goes back to the performance scorecard, which has a list of maybe 40 different targets. Leakage would be there, as well as number of houses, kilometres of pipe replaced, plants improved and all that kind of stuff.
Comment on this
Of those, some are obviously linked to local authority pay scales. Of the 3,000, how many are on the PRA scale?
Comment on this
There were approximately 3,200 people on the PRA last year.
Comment on this
Staff transfer from the local authorities all the time. That is why the figure changes all the time.
Comment on this
Correct me if I am wrong but I understand only 18 staff members did not receive a pay-related allowance. Were they all fully employed or were any of them on long-term leave?
Comment on this
I do not know the full details, but obviously that was done around performance at the end of the day. In some cases they may have been on leave, but I would have to check that.
Comment on this
I ask Mr. McCarthy to come back to us on that because it is important. It has been referenced that not all staff received the allowance. It is important that if staff did not receive it because they were on long-term leave-----
Comment on this
I ask the witnesses to come back to the committee and clarify that.
I turn to the issue of Mr. Gleeson's remuneration, which people will find extraordinary. I heard what he said regarding the rationale for it, and the independent review that was carried out last year. Was the board fully in agreement with it?
Comment on this
Yes. Like I said, there was an independent review carried out by a committee appointed by the Department of public expenditure. It reported to the Department and that information was transferred to our board.
Comment on this
It was benchmarked against all the other semi-State organisations and various CEOs were banded at specific bands. I do not have the specific details but they are available through the Government Department.
Comment on this
Our HR department, not me, submitted information as to the size of the company, number of employees, turnover and capital investment plans. That would have been benchmarked. All of the semi-State organisations were involved in this programme. It was the senior post remuneration committee and its report is available on the website.
Comment on this
Going forward, it will be related to performance. Any future increments will be related to performance but that was a benchmark brought in after the independent board assessed what should the CEO of Uisce Éireann receive, given the responsibilities, number of staff and financial responsibilities. The independent board assessed that and suggested a band. I am not sure what the numbers were, but it was a band of what the salary should be. That was submitted to our board and it then made a recommendation to the Minister who signed off on it.
Comment on this
Mr. Gleeson's pay was also included in that agreement. Will it go up 3% next year and a further 3%-----
Comment on this
No, it is not automatic. It will be related to performance.
Comment on this
It is related to performance. I want to touch on the issue of leakages. A figure of 30% was given for leakage within the system.
Comment on this
The leakage figure is at its lowest ever nationally.
Comment on this
When we came in in 2014, the leakage figure was at 37% in the greater Dublin area and now it is at 29%. Nationally, which includes the greater Dublin area, the leakage figure went from 49% to 36%.
Comment on this
Is there complete visibility of the major leaks within the system? Has that been established?
Comment on this
No. Leakage is an ongoing activity. Roughly 75% of the spend every single year on leakage is just to try to hold the leakage levels where they are. We have what is called the natural rate of rise. If we stopped all of our leakage activities, leakage would rise between 2% and 3% a year, every year. Essentially, we are actively seeking leaks the whole time on a find-and-fix basis. As I said, 75% is just to hold what we have, and the lower our leakage gets, the more money we will have to put into holding what we have.
Comment on this
We do about 1.8 billion litres. Approximately 600 million litres are lost.
Comment on this
We know what the value of it is nationally.
Comment on this
I will get the figure for the Cathaoirleach. I have a figure in my head, but I am not sure it is exactly correct.
Comment on this
We spend approximately €1 billion a year between water and wastewater.
Comment on this
If we cut that in half, it gives €500 million, and if we take one third of that again-----
Comment on this
At the risk of being pedantic - I want to be accurate, however - we have what is called distribution input, which is the water plants make and put into the system, and we have all of our non-domestic customers who are metered and domestic customers who are metered. We make allowances for those who are not metered and we call that leakage. Technically, however, it is called unaccounted for water because we know that there are places where our data is not complete. That is an apparent loss. We also know that there are properties that are connected and using the water for good effect, but we do not know where the water is going.
Comment on this
These are huge percentages and figures with a huge financial impact. I am conscious of the hose-pipe ban over the summer. A number of members have alluded to it, as have the witnesses. It is not lost on people when they are being told to reduce water consumption that, at the same time, 36% is being wasted. That again highlights while some measures and positive actions have been taken to reduce leakage, it is still a massive issue. There was a call put out by Uisce Éireann over the summer for people to inform it of people who may be breaching the hose-pipe ban. How many calls or reports were received?
Comment on this
There were a very small number of calls into the contact centre on that. In fairness, when we engaged with people, most of them responded favourably.
Comment on this
I do. I will find it. In most cases, the responses were very good, and most people were contacting us just to make general inquiries.
Comment on this
We have never taken enforcement action. It is just about raising awareness.
Comment on this
I have the figures here so I will come back to the committee with them.
Comment on this
I am also awaiting figures related to the Environmental Protection Agency and Inland Fisheries Ireland.
Comment on this
We actually have the figures here. I can read them. We were prosecuted 11 times last year, seven times by Inland Fisheries Ireland and four times by the EPA. The total fines levied on us amounted to €66,250, and agreed costs, operational and legal, between ourselves and the EPA and the IFI, came to €49,306.
Comment on this
If it agreeable to our witnesses, we will open the discussion to a second round of shorter supplementary questions. Our first questioner is Deputy Neville.
Comment on this
I am surprised. The other members are not here.
I thank the witnesses for staying on. One area I want to focus on is operating costs, which stand at €1.1 billion. That is Uisce Éireann’s cost base. I notice there has been a lot of talk about employee costs, which make up about 20%, but the largest single cost, at about 30%, is hiring in contracted services. That cost stands at €359 million. Which is the largest contractor Uisce Éireann pays money to?
Comment on this
We could come back with those numbers. Some of this stuff is commercially sensitive because obviously competitors would not necessarily want to know how much business they are doing with Uisce Éireann. I will look at that and see whether it makes sense to come back with it.
Comment on this
When we have the Department of justice in here, we are given a similar line. The international protection accommodation services, IPAS, comes to mind because we were talking about it this morning. We talk about contractors and providers, and we always get a list of the top ten.
Comment on this
Most of that is accounted for by what we call design-build-operate contractors. When we took over a lot of the local authorities built plants under what we call design-build-operate. They did not necessarily have the skills internally to operate the plants.
They got contractors to design, build and then they operate the plant under a 25- or 30-year contract. We have a legacy of those and that is where a lot of that cost is. Ringsend, in Dublin, accounts for 40% of the country's wastewater treatment. That is a DBO and that is a large contract, so a significant amount of money would be going through that.
Comment on this
In Ringsend, for example, that is a third party operating and running that. There is no Uisce Éireann staff on that site.
Comment on this
We have Uisce Éireann on a sort of supervisory level observing how they are operating but, generally, it is mostly their staff, yes.
Comment on this
How many staff does Uisce Éireann have direct? It is probably here in the stats, but I ask the witnesses to remind me of the number of individual people.
Comment on this
How many contractors would the witnesses say operate?
Comment on this
Is that between construction or is the Deputy talking about operations as well?
Comment on this
I am just thinking of people who would be linked into the hired-out contracted services. I am just trying to get an idea of the scope of the element of contracted work.
Comment on this
We would have done an economic analysis probably back in 2020. At that point, we would have said that in any given day there were probably 10,000 people working on water services for the island of Ireland. That probably has gone up since, given that our capital spend has increased significantly.
Comment on this
That would include some capital construction employees as well delivering projects.
Comment on this
Even as a TD, but definitely as a councillor, you are very close to what happens on the ground. I know it would be a lot of the contractors. It is the operating teams and Ms Attridge's team who call the contractors and say, "Lads, we have a burst. Let's go." I was just trying to get a handle on that cost and even the larger contracts. Is GMC one of Uisce Éireann's contractors?
Comment on this
Yes, it would be on a framework. It would have competed for a framework and given us a set of rates to do the work and that, so-----
Comment on this
That is exactly the type of question I was coming to. Is GMC one of Uisce Éireann's major contractors?
Comment on this
In the greater Dublin area, GDA, it would be, yes.
Comment on this
Okay. How would GMC's contract work? Mr. Gleeson says there is a framework. Is it per hour or is it a sitting amount?
Comment on this
They are paid on a daily rate on time for an operational response but, primarily, in the greater Dublin area, although not Kildare, we have our own in-house resources that do the repairs from an operational perspective. GMC would then support from a planned perspective where we would need extra support to reduce leakage. It would come in for a large-----
Comment on this
Was that the case for the works in Ballymore over the August bank holiday?
Comment on this
There was a combination of in-house and outsourced resources to do the Ballymore repairs.
Comment on this
How does Uisce Éireann decide then for a job, from a cost perspective? Does it analyse each job like that and say how it is more cost-effective to do it in-house or external? What I am trying to get at is how Uisce Éireann knows we are getting best value for money
Comment on this
Some counties historically had an outsourced model for maintenance and repair. The likes of Kildare and Carlow-Kilkenny would have outsourced repair. We kind of inherited those models, and where they were working we have not changed them. We are keeping those models going, whereas other local authorities would have had maintenance and repair teams in place. We continue to do insourced maintenance and repair, supplementing it with contractors.
Comment on this
I am not trying to get at anyone, but would Uisce Éireann set out the task and the cost of the task? How is that done? Does it go, "That will cost X"?
Comment on this
That is in respect of undertaking capital works. We have our plan for RC4. As part of that, we developed out our contract and procurement strategy for how we will deliver those works. As Ms Attridge said, there are key areas where we have internal staff available to do them. That is always our first course of action where those staff are available. The Deputy mentioned the Ballymore Eustace pipeline repair.
Comment on this
This time is the third year we have undertaken those repair activities. The first year we did it it was very significant and was probably primarily done with our external contracting partner, GMC, and the same the second year. Towards this year, half of the repair works were actually undertaken by our own staff. It is a really good example of where we were able to learn from our contracting partner, benefit from the experience of having done it a third time and then transfer some of that capability to our own staff so that we are able to do more of that going forward.
For a general stretch of main that has to be done, we have a networks contract which probably would have been procured. There are framework rates there where it is a cost to undertake this particular activity. In that regard, we would have gone through a procurement process where the contractor bears some of the risk of completing that work. We have multiple options, and our project teams deem then what is most appropriate in the particular scenario because there can be factors at play in terms of time and compliance issues, depending on what pressures are on or what other activities are in the area. All the time we endeavour to achieve the best value for the taxpayer.
Comment on this
In that context, I have one last question for Mr. McCarthy. Do we have a budget for next year? Is there a revenue budget already set for 2027? Is there an operating cost and then is there a target EBITDA? I know I focused on that EBITDA, but it just haunts me a little because it is just so big in the context of the overall revenue and ties back into the question I just asked. How do we ensure we are getting value for money if we know we have so much room to work with? I used the word "fat" earlier but, ultimately, when one third of your revenue becomes profit, that is a lot of scope for costs to go over. It is just around the budget. That is-----
Comment on this
We do not work off a typical profit-loss budget that other companies would work off. Mr. McCarthy will explain that.
Comment on this
I think I have already explained it to the Deputy, to be fair, in terms of the way any profits we have are reinvested back in and come off the Exchequer requirements. Obviously, we would have made our submission to the Department in terms of our budget requirements for 2027 and we are working off a business plan. That business plan is built through the regulatory model as well, and that was approved by the Minister last December. The next one is due for review and approval again coming up to the end of this year, and that covers a five-year period. It is worth noting we did receive our capital allocation for next year in full, which is, I think, €1.4 billion directly, through the Vote process. On the operating expense, OpEx, side, we asked for €912 million and received €879 million, so it is slightly-----
Comment on this
It is a big decrease, absolutely, and it will be a challenge given the market as well at the moment in terms of energy and all that.
Comment on this
I am sure there is a logic behind it, but it is worth noting. I thank the witnesses for explaining the budgetary process.
Comment on this
I want to go back to this year, 2026. Overall, I think there is a Vote on a new line in the expenditure for Irish Water. A sum of €2.25 billion is what is in that total Vote. Is that performance related? Is there any productivity or business plan? How do we know what value for money we are getting there in 2026? Are there any rules or stipulations put in place by the Government when it hands over that amount of money as to what Uisce Éireann has to do for the year?
Comment on this
The CRU, our economic regulator, would-----
Comment on this
I want to know then if that is where Uisce Éireann has failed. Is that 16 out of the 18 that were due to be passed?
Comment on this
It was 20 out of 24. Two were very close.
Comment on this
This year, how is it going? There are 16, where Uisce Éireann got €2.25 billion.
Comment on this
Will Uisce Éireann do everything that was outlined that it would spend that money on in the programme expenditure? It will-----
Comment on this
Mr. McCarthy said "absolutely"-----
Comment on this
"Absolutely" I understand the question-----